20179 W RINALDI ST 150 91326

Certificate Information: 20179 W RINALDI ST 150 91326

Application / Permit
18016-10000-36665
Plan Check / Job No.
B18LA24338
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Tenant improvement to (E) restaurant space. New mechanical platform.
Permit Issued
Issued on 6/6/2019
Issuing Office
Metro
Current Status
Permit Finaled on 1/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2018 APPLICANT
Assigned to Plan Check Engineer 11/29/2018 RODOLFO ARIAS
Corrections Issued 12/3/2018 RODOLFO ARIAS
Quality Review Completed 12/7/2018 GARO TELMI
Disabled Access Plans Picked Up 12/7/2018 APPLICANT
Green Plans Picked Up 1/14/2019 APPLICANT
Applicant returned to address corrections 1/29/2019 RODOLFO ARIAS
Plan Check Approved 5/28/2019 RODOLFO ARIAS
Issued 6/6/2019 LADBS
Permit Finaled 1/21/2020 ROBERT COLE

Permit Application Clearance Information

Address approval Cleared 1/14/2019 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 1/14/2019 NAZILA NOORIFAR
"D" conditions Cleared 1/17/2019 LATANYA ROUX
"T" removal Cleared 1/17/2019 LATANYA ROUX
CPC Cleared 1/17/2019 LATANYA ROUX
DAS Clearance Cleared 1/17/2019 RODOLFO ARIAS
Food Service Establishment Cleared 1/22/2019 RAMESHBHAIR PATEL
Sewer availability Cleared 1/25/2019 KAREN LE
Green Code Cleared 1/29/2019 NEGAR NEJAD
Fire Marshall Fire Life Safety Cleared 2/22/2019 OSCAR SALGADO JR
Specific Plan Cleared 3/28/2019 CHRISTINE BUSTILLOS
Food establishment approval Cleared 5/28/2019 LACDHS APPROVED

Contact Information

Architect Kelly,, George William; Lic. No.: C26144 1107 S WINDSOR BLVD      LOS ANGELES, CA 90019

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2019 Corrections Issued MILLARD ARDOIN
Footing/Foundation/Slab 7/19/2019 Corrections Issued ROBERT COLE
Green Building Rough 7/31/2019 Not Ready for Inspection MILLARD ARDOIN
Verify Sprinkler Sign Off 7/31/2019 Not Ready for Inspection MILLARD ARDOIN
Wood Frame 7/31/2019 Partial Approval MILLARD ARDOIN
Drywall Nailing 8/14/2019 Partial Inspection ROBERT COLE
Light Gage Steel Frame 8/22/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 8/28/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/29/2019 Corrections Issued ROBERT COLE
Drywall Nailing 9/6/2019 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/12/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 9/12/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 9/12/2019 Partial Inspection ROBERT COLE
Verify Sprinkler Sign Off 9/12/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 9/13/2019 Partial Approval ROBERT COLE
Drywall Nailing 9/25/2019 Partial Approval ROBERT COLE
Drywall Nailing 10/3/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 10/3/2019 Partial Inspection ROBERT COLE
Drywall Nailing 10/8/2019 Corrections Issued ROBERT COLE
Light Gage Steel Frame 10/10/2019 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 10/10/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 10/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/22/2019 Partial Inspection ROBERT COLE
T-Bar Ceiling 10/22/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 10/28/2019 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 10/28/2019 Partial Inspection ROBERT COLE
T-Bar Ceiling 10/28/2019 Partial Inspection ROBERT COLE
Light Gage Steel Frame 10/30/2019 Partial Approval ROBERT COLE
T-Bar Ceiling 10/30/2019 Not Ready for Inspection ROBERT COLE
Drywall Nailing 11/4/2019 Partial Approval ROBERT COLE
Light Gage Steel Frame 11/4/2019 Approved ROBERT COLE
T-Bar Ceiling 11/4/2019 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 11/27/2019 Not Ready for Inspection ROBERT COLE
T-Bar Ceiling 12/16/2019 Partial Inspection DANNY RODRIGUEZ
T-Bar Ceiling 12/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 12/20/2019 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 12/27/2019 Off-Hour Fees Due
T-Bar Ceiling 12/27/2019 Partial Approval ROBERT COLE
Final 12/31/2019 Partial Inspection ROBERT COLE
Green Building Final 12/31/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 12/31/2019 Not Ready for Inspection ROBERT COLE
SGSOV-Seismic Gas S/O Valve 12/31/2019 SGSOV Not Ready ROBERT COLE
Smoke Detectors 12/31/2019 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 12/31/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 12/31/2019 Partial Approval ROBERT COLE
Final 1/6/2020 Partial Inspection ROBERT COLE
Green Building Final 1/6/2020 Not Ready for Inspection ROBERT COLE
Green Building Rough 1/6/2020 Approved ROBERT COLE
SGSOV-Seismic Gas S/O Valve 1/6/2020 SGSOV Approved ROBERT COLE
Smoke Detectors 1/6/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 1/6/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 1/6/2020 Not Ready for Inspection ROBERT COLE
Final 1/10/2020 Partial Inspection DANNY RODRIGUEZ
Green Building Final 1/10/2020 Approved DANNY RODRIGUEZ
Smoke Detectors 1/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/10/2020 Approved DANNY RODRIGUEZ
Wood Frame 1/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/14/2020 Partial Inspection ROBERT COLE
Final 1/16/2020 Not Ready for Inspection ROBERT COLE
Smoke Detectors 1/16/2020 Approved ROBERT COLE
Wood Frame 1/16/2020 Approved ROBERT COLE
Final 1/21/2020 Permit Finaled ROBERT COLE