1240 W 29TH ST 90007
Certificate Information: 1240 W 29TH ST 90007
- Application / Permit
- 18016-10000-36521
- Plan Check / Job No.
- B18LA24274
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Hotel
- Work Description
- Soft-story retrofit per LABC Chapter 93. Install steel cantilever columns and shear wall. Verify portion of building retrofitted under permit 15016-30000-01622 meets the minimum requirements of LABC Chapter 93.
- Permit Issued
- Issued on 2/12/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/4/2020
Permit Application Status History
| Submitted | 11/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2018 | MANUEL MONTUFAR |
| Corrections Issued | 12/11/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 12/12/2018 | SAI KHUM |
| Building Plans Picked Up | 12/17/2018 | APPLICANT |
| Plan Check Approved | 8/16/2019 | MANUEL MONTUFAR |
| Issued | 2/12/2020 | LADBS |
| OK for CofC | 12/3/2020 | MARK FERRARI |
| CofC Issued | 12/4/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/16/2019 | MANUEL MONTUFAR |
| Housing rent stabilization | Cleared | 2/11/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/16/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 4/28/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 5/1/2020 | Partial Approval | DARRYL ARNOLD |
| Wood Frame | 5/5/2020 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 5/6/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/6/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/14/2020 | Partial Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/14/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 5/14/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/14/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/15/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 5/21/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 5/21/2020 | Partial Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/29/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 6/25/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 7/20/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 7/20/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 7/21/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 7/21/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 7/22/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 7/22/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/23/2020 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 7/27/2020 | Partial Inspection | DARRYL ARNOLD |
| Final | 9/21/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| METHANE-Final | 9/21/2020 | Approved | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 9/21/2020 | SGSOV Approved | FELIX CEBALLOS |
| Smoke Detectors | 9/21/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| Final | 9/28/2020 | Conditional Approval | MARK FERRARI |
| Smoke Detectors | 9/28/2020 | Approved | MARK FERRARI |
| Final | 12/3/2020 | OK for CofC | MARK FERRARI |