SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL TWO (N) STEEL MOMENT FRAMES
Permit Issued
Issued on 5/4/2020
Issuing Office
Metro
Current Status
CofC Issued on 4/15/2021

Permit Application Status History

Submitted 11/8/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 HANS SANTIAGO
Corrections Issued 12/10/2018 HANS SANTIAGO
Quality Review Completed 12/11/2018 SAI KHUM
Building Plans Picked Up 1/3/2019 APPLICANT
Plan Check Approved 1/25/2019 Andrew Santiago
Issued 5/4/2020 LADBS
OK for CofC 3/3/2021 KENNETH ROBERTS
CofC Issued 4/15/2021 KENNETH ROBERTS

Permit Application Clearance Information

Housing rent stabilization Cleared 3/26/2020 PHILLIP MUNGUIA

Contact Information

Contractor Sks Construction; Lic. No.: 720390-B 5104 GARDEN GROVE AVE      TARZANA, CA 91356
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Steel/Welding 7/17/2020 No Access for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 7/23/2020 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/29/2020 Conditional Approval VAHE KELEDJIAN
Deputy Reinf. Concrete 8/3/2020 Approved JOE VELASQUEZ
Deputy Steel/Welding 9/15/2020 No Access for Inspection JOE VELASQUEZ
Wood Frame 9/18/2020 Corrections Issued JOE VELASQUEZ
Wood Frame 9/25/2020 Partial Approval JOE VELASQUEZ
Interior/Exterior Lathing 10/8/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 10/8/2020 Corrections Issued JOE VELASQUEZ
Deputy Steel/Welding 10/15/2020 No Access for Inspection JOE VELASQUEZ
Interior/Exterior Lathing 10/20/2020 Approved JOE VELASQUEZ
Wood Frame 10/20/2020 Partial Approval JOE VELASQUEZ
Final 11/17/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 11/17/2020 Not Ready for Inspection JOE VELASQUEZ
Final 2/26/2021 Conditional Approval KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Not Ready KENNETH ROBERTS
Smoke Detectors 2/26/2021 Approved KENNETH ROBERTS
Final 3/3/2021 OK for CofC KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 3/3/2021 SGSOV No Gas KENNETH ROBERTS