15201 W VICTORY BLVD 91411
Certificate Information: 15201 W VICTORY BLVD 91411
- Application / Permit
- 18016-10000-36229
- Plan Check / Job No.
- B18LA24027
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING PLYWOOD SHEAR WALLS
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/11/2023
Permit Application Status History
| Submitted | 11/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | HANS SANTIAGO |
| Corrections Issued | 12/26/2018 | HANS SANTIAGO |
| Quality Review Completed | 12/28/2018 | SAI KHUM |
| Building Plans Picked Up | 1/29/2019 | APPLICANT |
| Plan Check Approved | 1/21/2021 | ANDREW SANTIAGO |
| Issued | 3/17/2021 | APPLICANT |
| OK for CofC | 10/14/2022 | KENNETH ROBERTS |
| CofC Issued | 1/11/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/23/2021 | STEVEN HOFSTAD |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | 17321 MURPHY AVENUE #240 IRVINE, CA 92614 |
| Engineer | Bozorgnia,, Behrouz; Lic. No.: C79581 | 1557 WESTWOOD BLVD 145 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2021 | Partial Inspection | DANIEL VARNUM |
| Deputy Reinf. Concrete | 4/14/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/21/2021 | Conditional Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Approved | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 4/21/2021 | Approved | DANIEL VARNUM |
| Wood Frame | 4/21/2021 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 4/23/2021 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/28/2021 | Approved | DANIEL VARNUM |
| Final | 7/22/2021 | Corrections Issued | KENNETH ROBERTS |
| Final | 7/22/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 7/22/2021 | Approved | KENNETH ROBERTS |
| Final | 7/26/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Corrections Issued | KENNETH ROBERTS |
| Final | 10/14/2022 | OK for CofC | KENNETH ROBERTS |