3905 S STEVELY AVE 90008
Certificate Information: 3905 S STEVELY AVE 90008
- Application / Permit
- 18016-10000-36165
- Plan Check / Job No.
- B18LA23976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 2 STEEL MOMENT FRAMES
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Current Status
- CofC Issued on 10/20/2022
Permit Application Status History
| Submitted | 11/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | HANS SANTIAGO |
| Corrections Issued | 12/31/2018 | HANS SANTIAGO |
| Quality Review Completed | 1/2/2019 | SAI KHUM |
| Building Plans Picked Up | 1/24/2019 | APPLICANT |
| Plan Check Approved | 6/3/2019 | ANDREW SANTIAGO |
| Issued | 6/18/2021 | APPLICANT |
| OK for CofC | 3/21/2022 | DARRYL ARNOLD |
| CofC Issued | 10/20/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/31/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Mercury Construction Inc; Lic. No.: 1004692-B | 3401 NORTH MISSION ROAD #1 LOS ANGELES, CA 90031 |
| Engineer | Valencia,, Leon; Lic. No.: S2107 | 5220 SANTA MONICA BLVD STE 202 LOS ANGELES, CA 90029 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/29/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 9/10/2021 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 9/13/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 9/23/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/27/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/14/2021 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 10/14/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 10/14/2021 | Partial Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 10/27/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 11/2/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/13/2021 | Corrections Issued | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 1/13/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 1/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/3/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 3/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/21/2022 | OK for CofC | DARRYL ARNOLD |
| Smoke Detectors | 3/21/2022 | Approved | DARRYL ARNOLD |