1640 E MARENGO ST 1st Floor 90033
Certificate Information: 1640 E MARENGO ST 1st Floor 90033
- Application / Permit
- 18016-10000-35700
- Plan Check / Job No.
- B18LA23622
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- NON STRUCTURAL TENANT IMPROVEMENT AND CHANGE OF USE FROM RESTAURANT TO MEDICAL OFFICES
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2018 | VU NGUYEN |
| Corrections Issued | 11/2/2018 | VU NGUYEN |
| Plan Check Approved | 11/16/2018 | VU NGUYEN |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 12/23/2020 | ERNESTO CORRAL |
| CofO in Progress | 12/23/2020 | ERNESTO CORRAL |
| CofO Issued | 12/23/2020 | ERNESTO CORRAL |
| Permit Finaled | 12/23/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 11/2/2018 | IVORY CHAMBESHI |
| ZA Case | Cleared | 11/2/2018 | IVORY CHAMBESHI |
| ZA Case | Cleared | 11/2/2018 | IVORY CHAMBESHI |
| ZA Case | Cleared | 11/2/2018 | IVORY CHAMBESHI |
| ZA Case | Cleared | 11/2/2018 | IVORY CHAMBESHI |
| Project located in CRA area | Cleared | 11/7/2018 | JIM URQUHART |
Contact Information
| Architect | , ; Lic. No.: C25474 | , |
| Contractor | D R H Construction; Lic. No.: 964984-B | 2021 3RD STREET UNIT H RIVERSIDE, CA 92507 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/13/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 2/21/2020 | Conditional Approval | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 2/24/2020 | Approved | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 2/26/2020 | Approved | LANNY MERRICK |
| Drywall Nailing | 3/3/2020 | Partial Approval | RONALD PACHECO |
| Final | 6/8/2020 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Concrete Frame | 6/8/2020 | Approved | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 6/8/2020 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 6/8/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 6/12/2020 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 6/12/2020 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 6/12/2020 | Approved | RONALD PACHECO |
| Final | 6/17/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 12/23/2020 | OK to Issue CofO | ERNESTO CORRAL |