8955 N COLUMBUS AVE 91343
Certificate Information: 8955 N COLUMBUS AVE 91343
- Application / Permit
- 18016-10000-34924
- Plan Check / Job No.
- B18LA23074
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIVISION 93. INSTALL ONE SMF-RBS AND ONE CANTILEVER COLUMN.
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofC Issued on 5/10/2021
Permit Application Status History
| Submitted | 10/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2018 | JOHN FRANCIA |
| Corrections Issued | 12/11/2018 | JOHN FRANCIA |
| Quality Review Completed | 12/14/2018 | SAI KHUM |
| Building Plans Picked Up | 1/29/2019 | APPLICANT |
| Plan Check Approved | 6/4/2020 | JOHN FRANCIA |
| Issued | 10/14/2020 | APPLICANT |
| OK for CofC | 4/19/2021 | KENNETH ROBERTS |
| CofC Issued | 5/10/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 9/1/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Bozorgnia,, Behrouz; Lic. No.: C79581 | 1557 WESTWOOD BLVD 145 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2020 | Partial Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 12/23/2020 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 12/24/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 12/24/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 12/24/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 1/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 1/21/2021 | Approved | DANIEL VARNUM |
| Final | 3/8/2021 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/8/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 3/8/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 3/31/2021 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 3/31/2021 | Approved | DANIEL VARNUM |
| Final | 4/19/2021 | OK for CofC | KENNETH ROBERTS |