825 S BEDFORD ST 90035

Certificate Information: 825 S BEDFORD ST 90035

Application / Permit
18016-10000-34651
Plan Check / Job No.
B18LA22891
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT PER LABC CHAPTER 93. (1) ORDINARY MOMENT FRAME (OMF) (1) WOOD SHEAR WALL WORK IS DONE AT NORTH & SOUTH SIDE TUCK-UNDER PARKING AREAS AT FIRST FLOOR.
Permit Issued
Issued on 1/22/2021
Issuing Office
Metro
Current Status
CofC Issued on 3/17/2022

Permit Application Status History

Submitted 10/25/2018 APPLICANT
Assigned to Plan Check Engineer 11/21/2018 ALFREDO JARA
Corrections Issued 11/27/2018 ALFREDO JARA
Quality Review Completed 11/29/2018 SAI KHUM
Building Plans Picked Up 12/6/2018 APPLICANT
Plan Check Approved 12/18/2018 ALFREDO JARA
Issued 1/22/2021 APPLICANT
OK for CofC 11/30/2021 DARRYL ARNOLD
CofC Issued 3/17/2022 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 11/25/2020 STEVEN HOFSTAD

Contact Information

Contractor Sks Construction; Lic. No.: 720390-B 5104 GARDEN GROVE AVE      TARZANA, CA 91356
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/23/2021 Approved DARRYL ARNOLD
Deputy Steel/Welding 7/16/2021 Conditional Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 9/24/2021 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 9/28/2021 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 9/29/2021 Corrections Issued DARRYL ARNOLD
Footing/Foundation/Slab 10/4/2021 Approved BRUCE CAMPBELL
Structural Steel Frame 10/4/2021 Approved BRUCE CAMPBELL
Wood Frame 10/4/2021 Approved BRUCE CAMPBELL
Deputy Reinf. Concrete 10/5/2021 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 10/6/2021 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 10/6/2021 Conditional Approval MARK FERRARI
Wood Frame 10/14/2021 Approved MARK FERRARI
Interior/Exterior Lathing 10/25/2021 Conditional Approval DARRYL ARNOLD
Final 11/30/2021 OK for CofC DARRYL ARNOLD
METHANE-Final 11/30/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 11/30/2021 Approved DARRYL ARNOLD