1277 S BARRY AVE 90025
Certificate Information: 1277 S BARRY AVE 90025
- Application / Permit
- 18016-10000-34225
- Plan Check / Job No.
- B18LA22632
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (4) STEEL SPECIAL CANTILEVER COLUMNS AND 3 SHEARWALLS TO EXISTING 3-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/16/2020
Permit Application Status History
| Submitted | 10/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2018 | MICHAEL PEREZ |
| Corrections Issued | 12/10/2018 | MICHAEL PEREZ |
| Quality Review Completed | 12/14/2018 | SAI KHUM |
| Building Plans Picked Up | 12/26/2018 | APPLICANT |
| Plan Check Approved | 5/3/2019 | MICHAEL PEREZ |
| Issued | 1/7/2020 | LADBS |
| OK for CofC | 6/12/2020 | SORIN CIRSTOIU |
| CofC Issued | 6/16/2020 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/16/2019 | MICHAEL SOTO |
Contact Information
| Contractor | Basseri Engineering & Construction; Lic. No.: 724559-B | 5250 W CENTRY BLVD #300 LOS ANGELES, CA 90045 |
| Engineer | Basseri,, Siavash; Lic. No.: C45487 | 5250 W CENTURY BLVD STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2020 | Approved | JOHN DODGE |
| Deputy Steel/Welding | 3/10/2020 | No Access for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 3/12/2020 | Partial Approval | JOHN DODGE |
| Footing/Foundation/Slab | 3/23/2020 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 3/24/2020 | Approved | JOHN DODGE |
| Wood Frame | 4/3/2020 | Corrections Issued | JOHN DODGE |
| Footing/Foundation/Slab | 4/17/2020 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 4/17/2020 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 4/28/2020 | No Access for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 4/29/2020 | Approved | JOHN DODGE |
| Wood Frame | 5/5/2020 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 5/22/2020 | Not Ready for Inspection | ALAN NOVAK |
| Interior/Exterior Lathing | 5/26/2020 | Partial Approval | SORIN CIRSTOIU |
| Final | 6/12/2020 | OK for CofC | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/12/2020 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 6/12/2020 | Approved | SORIN CIRSTOIU |