14603 W DELANO ST 91411
Certificate Information: 14603 W DELANO ST 91411
- Application / Permit
- 18016-10000-32808
- Plan Check / Job No.
- B18LA21627
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. USING 2 NEW SCCS.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofC Issued on 11/10/2020
Permit Application Status History
| Submitted | 10/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 11/14/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 11/15/2018 | SAI KHUM |
| Building Plans Picked Up | 11/19/2018 | APPLICANT |
| Plan Check Approved | 12/19/2018 | SAMUEL GONZALEZ |
| Issued | 7/17/2020 | APPLICANT |
| OK for CofC | 10/16/2020 | JONATHAN QUACH |
| CofC Issued | 11/10/2020 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/31/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Dvin & Co Inc; Lic. No.: 1043413-B | 614 E GARFIELD AVE #3 GLENDALE, CA 91205 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 8/13/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/14/2020 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 8/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/19/2020 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 8/24/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 8/25/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/25/2020 | Partial Approval | JOE VELASQUEZ |
| Insulation | 8/31/2020 | Partial Approval | JOE VELASQUEZ |
| Structural Steel Frame | 8/31/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 9/11/2020 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/14/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 9/23/2020 | Approved | JOE VELASQUEZ |
| Final | 10/16/2020 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/16/2020 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 10/16/2020 | Approved | JONATHAN QUACH |