1029 S UNION AVE 1-30 90015
Certificate Information: 1029 S UNION AVE 1-30 90015
- Application / Permit
- 18016-10000-32565
- Plan Check / Job No.
- B18LA21500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (4) STEEL SPECIAL CANTILEVER COLUMNS
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- CofC Issued on 5/10/2021
Permit Application Status History
| Submitted | 10/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 11/27/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 11/30/2018 | SAI KHUM |
| Building Plans Picked Up | 12/4/2018 | APPLICANT |
| Plan Check Approved | 6/19/2019 | SAMUEL GONZALEZ |
| Issued | 12/30/2020 | APPLICANT |
| OK for CofC | 4/28/2021 | DARRYL ARNOLD |
| CofC Issued | 5/10/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 5/21/2019 | JIM URQUHART |
| HPOZ | Cleared | 6/12/2019 | MAX LODER |
| Housing rent stabilization | Cleared | 12/29/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2021 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 2/26/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 2/26/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 4/1/2021 | Approved | DARRYL ARNOLD |
| Reinforced Concrete Frame | 4/1/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 4/1/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/1/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 4/7/2021 | Approved | DARRYL ARNOLD |
| Reinforced Concrete Frame | 4/7/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 4/7/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/7/2021 | Approved | DARRYL ARNOLD |
| Reinforced Concrete Frame | 4/13/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 4/13/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/13/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/22/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/28/2021 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/28/2021 | Approved | DARRYL ARNOLD |