16025 W GAULT ST 91406
Certificate Information: 16025 W GAULT ST 91406
- Application / Permit
- 18016-10000-32456
- Plan Check / Job No.
- B18LA21442
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETORFIT PER LABC CHAPTER 93. (4) SCCS
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/7/2021
Permit Application Status History
| Submitted | 10/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 11/27/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 11/30/2018 | SAI KHUM |
| Building Plans Picked Up | 12/6/2018 | APPLICANT |
| Plan Check Approved | 5/28/2019 | SAMUEL GONZALEZ |
| Issued | 3/2/2020 | LADBS |
| OK for CofC | 6/23/2021 | KENNETH ROBERTS |
| CofC Issued | 10/7/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/24/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | L L K Construction Inc; Lic. No.: 894375-B | 14148 KITTRIDGE ST VAN NUYS, CA 91405 |
| Engineer | Stovner,, Eric Christian; Lic. No.: S4204 | 1195 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2020 | Approved | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 3/25/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 3/25/2020 | Partial Approval | FELIX CEBALLOS |
| Reinforced Concrete Frame | 3/25/2020 | Approved | FELIX CEBALLOS |
| Structural Steel Frame | 3/25/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 4/10/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/17/2020 | Approved | FELIX CEBALLOS |
| Interior/Exterior Lathing | 4/27/2020 | Approved | HAMID PISHEHVAR |
| Final | 3/30/2021 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 3/30/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 4/22/2021 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 4/22/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 4/22/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/4/2021 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 6/4/2021 | Approved | DANIEL VARNUM |
| Final | 6/23/2021 | OK for CofC | KENNETH ROBERTS |