424 S SHERBOURNE DR 90048

Certificate Information: 424 S SHERBOURNE DR 90048

Application / Permit
18016-10000-32097
Plan Check / Job No.
B18LA21229
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) STEEL ORDINARY MOMENT FRAMES.
Permit Issued
Issued on 1/19/2023
Issuing Office
Valley
Current Status
CofC Issued on 5/2/2025

Permit Application Status History

Submitted 10/3/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 TEODORO DIAZ RODRIGUEZ
Corrections Issued 11/21/2018 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 12/4/2018 SAI KHUM
Building Plans Picked Up 12/6/2018 APPLICANT
Plan Check Approved 1/15/2019 TEODORO DIAZ RODRIGUEZ
Issued 1/19/2023 APPLICANT
OK for CofC 4/24/2025 DARRYL ARNOLD
CofC Issued 5/2/2025 ERNESTO CORRAL

Permit Application Clearance Information

CPC Cleared 12/12/2018 STEVEN WECHSLER
Housing rent stabilization Cleared 11/22/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Dhe Best Construction Inc; Lic. No.: 1051288-B P O BOX 568      WOODLAND HILLS, CA 91365
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/15/2023 Partial Inspection VAHE KELEDJIAN
Pre-Inspection 10/25/2024 Corrections Issued DARRYL ARNOLD
Deputy Drilled-In Anchors 12/10/2024 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 12/16/2024 Approved DARRYL ARNOLD
Footing/Foundation/Slab 12/16/2024 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 12/16/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 12/26/2024 Approved DARRYL ARNOLD
Deputy Wood Construction 1/8/2025 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 1/14/2025 Approved DARRYL ARNOLD
Final 2/28/2025 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 2/28/2025 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 2/28/2025 Corrections Issued DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Not Ready DARRYL ARNOLD
Final 4/24/2025 OK for CofC DARRYL ARNOLD
METHANE-Final 4/24/2025 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 4/24/2025 Approved DARRYL ARNOLD