12053 W GUERIN ST 91604

Certificate Information: 12053 W GUERIN ST 91604

Application / Permit
18016-10000-31996
Plan Check / Job No.
B18LA21160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) SPECIAL STEEL CANTILEVERED COLUMNS
Permit Issued
Issued on 9/17/2020
Issuing Office
Current Status
CofC Issued on 6/22/2021

Permit Application Status History

Submitted 10/3/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 TEODORO DIAZ RODRIGUEZ
Corrections Issued 11/21/2018 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 12/4/2018 SAI KHUM
Building Plans Picked Up 12/18/2018 APPLICANT
Plan Check Approved 12/19/2018 TEODORO DIAZ RODRIGUEZ
Issued 9/17/2020 APPLICANT
OK for CofC 6/22/2021 JEFFREY DURAN
CofC Issued 6/22/2021 JEFFREY DURAN

Permit Application Clearance Information

Hold Cleared 11/5/2018 LOURDES RAMIRO
Housing rent stabilization Cleared 9/16/2020 PHILLIP MUNGUIA

Contact Information

Contractor Sandstone Builders Inc; Lic. No.: 946847-B 5721 RANCHITO AVE      VAN NUYS, CA 91401
Engineer Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 114 SHADOWHILL CIRCLE      SAN RAMON, CA 94583

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/22/2020 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 10/22/2020 Not Ready for Inspection JOE VELASQUEZ
Excavation/Setback/Form/Re-Bar 10/27/2020 Approved JONATHAN QUACH
Pre-Inspection 10/27/2020 Approved JONATHAN QUACH
Insulation 10/30/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 11/30/2020 Partial Approval HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Wood Construction 12/11/2020 No Access for Inspection JOE VELASQUEZ
Wood Frame 12/17/2020 Approved JOE VELASQUEZ
Interior/Exterior Lathing 12/31/2020 Approved DANIEL VARNUM
Final 2/4/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 2/4/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 2/4/2021 Not Ready for Inspection JOE VELASQUEZ
Final 3/9/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 3/9/2021 Not Ready for Inspection JOE VELASQUEZ
Final 6/22/2021 OK for CofC JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Approved JEFFREY DURAN
Smoke Detectors 6/22/2021 Approved JEFFREY DURAN