2600 S HOOVER ST 90007

Certificate Information: 2600 S HOOVER ST 90007

Application / Permit
18016-10000-31043
Plan Check / Job No.
B18LA20523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Alteration and minor addition and repair of existing SRO hotel building. Building into Publicly funded multifamily dwelling units. Conversion of existing historic 46 units into 27 units of low income housing and supportive services. New elevator to be provided.
Permit Issued
Issued on 3/26/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2018 APPLICANT
Assigned to Plan Check Engineer 9/26/2018 JOE VO
Corrections Issued 10/2/2018 JOE VO
Quality Review Completed 10/2/2018 LAWRENCE QUIRANTE
Green Plans Picked Up 10/2/2018 APPLICANT
Building Plans Picked Up 10/4/2018 APPLICANT
Disabled Access Plans Picked Up 10/11/2018 APPLICANT
Applicant returned to address corrections 11/1/2018 JOE VO
Plan Check Approved 3/22/2019 JOE VO
Issued 3/26/2019 LADBS
TCO Issued (Expire Date: 06-28-2022) 12/30/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 02-27-2023) 8/31/2022 ERNESTO CORRAL
CofO in Progress 9/14/2022 TED RIES
Permit Finaled 9/14/2022 TED RIES
CofO Issued 9/14/2022 TED RIES
Permit Finaled 9/14/2022 TED RIES

Permit Application Clearance Information

"Q" conditions Cleared 10/26/2018 EDBER MACEDO
Address approval Cleared 10/26/2018 NAZILA NOORIFAR
Sewer availability Cleared 10/26/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 11/1/2018 NAZILA NOORIFAR
Hydrant and Access approval Cleared 11/19/2018 GEORGE SUCHAND
DAS Clearance Cleared 12/18/2018 JOE VO
Green Code Cleared 12/19/2018 SARAH ABOULHOSN
Historic monument Cleared 1/2/2019 LAMBERT GIESSINGER
ZA Case Cleared 1/3/2019 SOPHIE GABEL-SCHEINBAU
Residential hotels Cleared 1/15/2019 MARITES CUNANAN
Historical monument Cleared 1/16/2019 JIM URQUHART
Project located in CRA area Cleared 1/16/2019 JIM URQUHART
Fire Marshall Fire Life Safety Cleared 2/4/2019 PEJMAN NOORI
Housing rent stabilization Cleared 2/7/2019 STEVEN HOFSTAD
Low Impact Development Cleared 3/21/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/21/2019 JEANIE LAM

Contact Information

Architect Michali,, Thomas Charles; Lic. No.: C12994 306 RAYMOND STREET      OJAI, CA 93023
Contractor Curtom - Dunsmuir A Joint Venture; Lic. No.: 782018-B 1128 NORTH LA BREA AVENUE      INGLEWOOD, CA 90302
Engineer Hershberg,, Mark Aaron; Lic. No.: S5078 6080 CENTER DR STE 300      LOS ANGELES, CA 90045
Engineer Sutton,, Lynn Morris; Lic. No.: C18225 10 WEST MENDOCINO      STOCKTON, CA 95204

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2019 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 8/15/2019 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 8/16/2019 Order to Comply Issued JOEY BUCHANAN
Deputy Reinf. Concrete 8/20/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 9/6/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/9/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/9/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/10/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 9/10/2019 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Corrections Issued JOEY BUCHANAN
Deputy Drilled-In Anchors 9/19/2019 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 9/19/2019 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 9/23/2019 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 9/24/2019 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Partial Approval GRANT WOODS
Green Building Rough 10/24/2019 Not Ready for Inspection GRANT WOODS
METHANE-Rough 10/24/2019 Not Ready for Inspection GRANT WOODS
Green Building Rough 11/6/2019 Not Ready for Inspection RONALD PACHECO
METHANE-Rough 11/6/2019 Not Ready for Inspection RONALD PACHECO
Wood Frame 11/6/2019 Not Ready for Inspection RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Partial Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 11/26/2019 Partial Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 12/2/2019 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 12/12/2019 Corrections Issued RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 12/16/2019 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 12/23/2019 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 2/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/7/2020 Partial Approval CHRISTOPHER DELLEFIELD
Structural Steel Frame 2/19/2020 Approved RAFAEL ESPINOZA
Insulation 3/18/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Insulation 3/19/2020 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 5/14/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Pre-Inspection 5/28/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 6/10/2020 Not Ready for Inspection LEOPOLDO MENDOZA
METHANE-Rough 6/10/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 6/10/2020 Partial Approval LEOPOLDO MENDOZA
Green Building Rough 6/17/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Insulation 6/17/2020 Partial Approval LEOPOLDO MENDOZA
METHANE-Rough 6/17/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 6/17/2020 Partial Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/6/2020 Corrections Issued LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/9/2020 Partial Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/13/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/16/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 8/4/2020 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Approval LEOPOLDO MENDOZA
Green Building Rough 8/13/2020 Not Ready for Inspection LEOPOLDO MENDOZA
METHANE-Rough 8/13/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 8/13/2020 Partial Approval LEOPOLDO MENDOZA
Pre-Inspection 8/25/2020 Partial Approval LEOPOLDO MENDOZA
Wood Frame 9/10/2020 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 9/22/2020 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 9/22/2020 Partial Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 9/23/2020 Conditional Approval RUSSELL BONVOULOIR
Green Building Rough 9/23/2020 Approved LEOPOLDO MENDOZA
Insulation 9/23/2020 Partial Approval LEOPOLDO MENDOZA
METHANE-Rough 9/23/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 9/23/2020 Partial Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 9/29/2020 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Not Ready for Inspection LEOPOLDO MENDOZA
METHANE-Rough 10/5/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 10/5/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 10/7/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 10/8/2020 Partial Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 10/8/2020 Conditional Approval LEOPOLDO MENDOZA
METHANE-Rough 10/14/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 10/14/2020 Partial Approval LEOPOLDO MENDOZA
METHANE-Rough 10/21/2020 Approved LEOPOLDO MENDOZA
Wood Frame 10/21/2020 Partial Approval LEOPOLDO MENDOZA
Wood Frame 10/23/2020 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 10/29/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Drywall Nailing 11/4/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 11/9/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 12/4/2020 Corrections Issued LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 12/21/2020 Not Ready for Inspection RUSSELL BONVOULOIR
Deputy Reinf. Concrete 12/24/2020 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 12/30/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 12/31/2020 Conditional Approval LANNY MERRICK
Wood Frame 1/4/2021 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 1/12/2021 Partial Approval LEOPOLDO MENDOZA
Wood Frame 1/14/2021 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 1/20/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/29/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 2/3/2021 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 2/12/2021 Not Ready for Inspection LANNY MERRICK
Drywall Nailing 2/18/2021 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 3/3/2021 Conditional Approval RUSSELL BONVOULOIR
Drywall Nailing 3/5/2021 Partial Approval LANNY MERRICK
Drywall Nailing 3/9/2021 Not Ready for Inspection LANNY MERRICK
Drywall Nailing 3/15/2021 Partial Approval LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval LANNY MERRICK
Wood Frame 4/12/2021 Partial Approval LANNY MERRICK
Drywall Nailing 4/20/2021 Approved LANNY MERRICK
Excavation/Setback/Form/Re-Bar 4/20/2021 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 4/21/2021 Conditional Approval RUSSELL BONVOULOIR
Final 4/23/2021 Partial Inspection LANNY MERRICK
Green Building Final 4/23/2021 Approved LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved LANNY MERRICK
Smoke Detectors 4/23/2021 Approved LANNY MERRICK
Wood Frame 4/23/2021 Approved LANNY MERRICK
Insulation 5/18/2021 Approved LANNY MERRICK
Drywall Nailing 6/1/2021 Partial Approval LEOPOLDO MENDOZA
Insulation 6/2/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 9/2/2021 Conditional Approval LEOPOLDO MENDOZA
Pre-Inspection 11/17/2021 Partial Inspection RUSSELL BONVOULOIR
Pre-Inspection 11/22/2021 Order to Comply Issued RUSSELL BONVOULOIR
Special/Order Compliance 11/22/2021 Partial Approval RUSSELL BONVOULOIR
Final 12/28/2021 Partial Inspection RUSSELL BONVOULOIR
Final 5/3/2022 Conditional Approval RUSSELL BONVOULOIR
Special/Order Compliance 6/1/2022 Partial Inspection RUSSELL BONVOULOIR