3224 N CHAPMAN ST 90065

Certificate Information: 3224 N CHAPMAN ST 90065

Application / Permit
18016-10000-30994
Plan Check / Job No.
B18LA20491
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. USING 2 CANTILEVER COLUMNS.
Permit Issued
Issued on 5/11/2020
Issuing Office
Current Status
CofC Issued on 9/29/2020

Permit Application Status History

Submitted 9/28/2018 APPLICANT
Assigned to Plan Check Engineer 11/8/2018 CELESTE MORRIS
Corrections Issued 11/13/2018 CELESTE MORRIS
Quality Review Completed 11/19/2018 SAI KHUM
Building Plans Picked Up 12/12/2018 APPLICANT
Applicant returned to address corrections 5/8/2019 CELESTE MORRIS
Plan Check Approved 5/9/2019 CELESTE NGUYEN
Issued 5/11/2020 APPLICANT
OK for CofC 8/19/2020 MARK FERRARI
CofC Issued 9/29/2020 ERNESTO CORRAL

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 5/9/2019 JOE LUCKEY
Housing rent stabilization Cleared 3/31/2020 MICHAEL GREGERSON

Contact Information

Contractor Dvin & Co Inc; Lic. No.: 1043413-B 614 E GARFIELD AVE #3      GLENDALE, CA 91205
Engineer Farmand,, Anthony E; Lic. No.: C62595 2372 MORSE AVE STE 137      IRVINE, CA 92614

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2020 Corrections Issued MARK FERRARI
Deputy Steel/Welding 6/15/2020 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 7/1/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 7/7/2020 Corrections Issued MARK FERRARI
Structural Steel Frame 7/7/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 7/7/2020 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 7/9/2020 Approved MARK FERRARI
Footing/Foundation/Slab 7/9/2020 Corrections Issued MARK FERRARI
Wood Frame 7/17/2020 Approved VAHE KELEDJIAN
Wood Frame 7/22/2020 Corrections Issued MARK FERRARI
Deputy Wood Construction 7/23/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 8/3/2020 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/18/2020 SGSOV Not Ready MARK FERRARI
Final 8/19/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 8/19/2020 Approved MARK FERRARI