1054 S WOOSTER ST 90035

Certificate Information: 1054 S WOOSTER ST 90035

Application / Permit
18016-10000-29830
Plan Check / Job No.
B18LA19718
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT PER LABC CHAPTER 93. INSTALL HARDY PANELS.
Permit Issued
Issued on 3/31/2020
Issuing Office
Metro
Current Status
CofC Issued on 8/25/2021

Permit Application Status History

Submitted 9/14/2018 APPLICANT
Assigned to Plan Check Engineer 10/24/2018 JAIME OROZCO
Corrections Issued 10/31/2018 JAIME OROZCO
Quality Review Completed 11/2/2018 SAI KHUM
Building Plans Picked Up 11/6/2018 APPLICANT
Plan Check Approved 12/21/2018 JAIME OROZCO
Issued 3/31/2020 LADBS
OK for CofC 8/24/2021 BRUCE CAMPBELL
CofC Issued 8/25/2021 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 9/25/2019 PHILLIP MUNGUIA

Contact Information

Contractor Quakestrong; Lic. No.: 1037437-B 1213 LA BREA AVENUE      LOS ANGELES, CA 90019
Engineer Andy, J Alexander; Lic. No.: C84086       ,

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2021 Approved DARRYL ARNOLD
Deputy Drilled-In Anchors 5/6/2021 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 5/13/2021 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 5/17/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 6/28/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 6/28/2021 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 6/28/2021 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 6/30/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 7/19/2021 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Corrections Issued MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Conditional Approval BRUCE CAMPBELL
Interior/Exterior Lathing 8/10/2021 Conditional Approval DARRYL ARNOLD
Final 8/19/2021 Not Ready for Inspection BRUCE CAMPBELL
METHANE-Final 8/19/2021 Approved BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 8/19/2021 SGSOV Approved BRUCE CAMPBELL
Smoke Detectors 8/19/2021 Approved BRUCE CAMPBELL
Final 8/23/2021 Not Ready for Inspection BRUCE CAMPBELL
Final 8/24/2021 OK for CofC BRUCE CAMPBELL