6804 N BAIRD AVE 91335
Certificate Information: 6804 N BAIRD AVE 91335
- Application / Permit
- 18016-10000-29190
- Plan Check / Job No.
- B18LA19266
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL WOOD SHEAR WALLS.
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/16/2021
Permit Application Status History
| Submitted | 9/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2018 | VARAND SARKISIAN |
| Corrections Issued | 11/1/2018 | VARAND SARKISIAN |
| Quality Review Completed | 11/2/2018 | SAI KHUM |
| Building Plans Picked Up | 11/8/2018 | APPLICANT |
| Applicant returned to address corrections | 12/4/2018 | VARAND SARKISIAN |
| Plan Check Approved | 12/5/2018 | VARAND SARKISIAN |
| Issued | 8/20/2020 | APPLICANT |
| OK for CofC | 3/1/2021 | KENNETH ROBERTS |
| CofC Issued | 4/16/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 12/5/2018 | LATANYA ROUX |
| Housing rent stabilization | Cleared | 8/7/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2020 | Partial Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 9/4/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 10/22/2020 | Conditional Approval | KENNETH ROBERTS |
| Wood Frame | 10/26/2020 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 11/17/2020 | Approved | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 12/7/2020 | Approved | DANIEL VARNUM |
| Final | 12/14/2020 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 12/14/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 12/14/2020 | Approved | DANIEL VARNUM |
| Final | 12/23/2020 | Partial Approval | DANIEL VARNUM |
| Final | 3/1/2021 | OK for CofC | KENNETH ROBERTS |