1015 N ARDMORE AVE 90029
Certificate Information: 1015 N ARDMORE AVE 90029
- Application / Permit
- 18016-10000-29090
- Plan Check / Job No.
- B18LA19206
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 1 (N) ORDINERY MOMENT FRAME AND SHEAR WALLS.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/21/2020
Permit Application Status History
| Submitted | 9/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | VARAND SARKISIAN |
| Corrections Issued | 10/9/2018 | VARAND SARKISIAN |
| Quality Review Completed | 10/10/2018 | JAMESON LEE |
| Building Plans Picked Up | 10/18/2018 | APPLICANT |
| Plan Check Approved | 11/5/2018 | VARAND SARKISIAN |
| Issued | 3/6/2020 | LADBS |
| OK for CofC | 8/12/2020 | MARK FERRARI |
| CofC Issued | 8/21/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/13/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Youhanna, Labib; Lic. No.: S4549 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2020 | Corrections Issued | BRUCE CAMPBELL |
| Pre-Inspection | 6/16/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 7/6/2020 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 7/6/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 7/6/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/6/2020 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/9/2020 | Approved | MARK FERRARI |
| Drywall Nailing | 7/15/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/15/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 7/16/2020 | Conditional Approval | MARK FERRARI |
| Final | 8/11/2020 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 8/11/2020 | Approved | MARK FERRARI |
| Final | 8/12/2020 | OK for CofC | MARK FERRARI |