9022 N ORION AVE 91343
Certificate Information: 9022 N ORION AVE 91343
- Application / Permit
- 18016-10000-28336
- Plan Check / Job No.
- B18LA18767
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIV. 93: INSTALL STEEL MOMENT FRAME
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofC Issued on 8/18/2023
Permit Application Status History
| Submitted | 9/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | MANUEL MONTUFAR |
| Corrections Issued | 10/9/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 10/10/2018 | CELESTE MORRIS |
| Plan Check Approved | 1/11/2019 | MANUEL MONTUFAR |
| Issued | 8/20/2020 | APPLICANT |
| OK for CofC | 4/14/2023 | KENNETH ROBERTS |
| CofC Issued | 8/18/2023 | KENNETH ROBERTS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/9/2018 | MOTOUMI SASAKI |
| Housing rent stabilization | Cleared | 6/8/2020 | STEVEN HOFSTAD |
Contact Information
| Architect | Santillan,, Michael; Lic. No.: C23337 | 832 SANTIAGO ROAD COSTA MESA, CA 92626 |
| Contractor | Saunders Construction Inc; Lic. No.: 616856-B | 1760 MONROVIA AVE SUITE A-1 COSTA MESA, CA 92627 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/8/2020 | Partial Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 11/13/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 11/13/2020 | No Access for Inspection | DANIEL VARNUM |
| Wood Frame | 11/13/2020 | No Access for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 11/17/2020 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 11/17/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 11/18/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 11/24/2020 | Conditional Approval | DANIEL VARNUM |
| Structural Steel Frame | 12/7/2020 | Approved | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 12/18/2020 | Approved | DANIEL VARNUM |
| Deputy Wood Construction | 12/21/2020 | Conditional Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 1/8/2021 | Approved | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 4/12/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 4/12/2021 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 4/12/2021 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 4/12/2021 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 4/14/2021 | Conditional Approval | BRUCE CAMPBELL |
| Final | 6/25/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 6/25/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 4/14/2023 | OK for CofC | KENNETH ROBERTS |
| Smoke Detectors | 4/14/2023 | Approved | KENNETH ROBERTS |