13570 W CANTLAY ST 91405
Certificate Information: 13570 W CANTLAY ST 91405
- Application / Permit
- 18016-10000-28243
- Plan Check / Job No.
- B18LA18674
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 2 MOMENT FRAMES AND SHEAR WALLS.
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/18/2021
Permit Application Status History
| Submitted | 8/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2018 | DANIEL SANJUAN |
| Corrections Issued | 10/25/2018 | DANIEL SANJUAN |
| Quality Review Completed | 10/26/2018 | SAI KHUM |
| Building Plans Picked Up | 10/29/2019 | APPLICANT |
| Plan Check Approved | 1/15/2020 | DANIEL SANJUAN |
| Issued | 8/27/2020 | APPLICANT |
| OK for CofC | 2/22/2021 | KENNETH ROBERTS |
| CofC Issued | 3/18/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/6/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | 17321 MURPHY AVE #240 IRVINE, CA 92614 |
| Engineer | Behrouz, Bozorgnia; Lic. No.: C79581 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 10/6/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 10/6/2020 | Corrections Issued | JOE VELASQUEZ |
| Deputy Other (see comments) | 10/13/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 10/13/2020 | Partial Inspection | JONATHAN QUACH |
| Deputy Steel/Welding | 10/14/2020 | No Access for Inspection | JOE VELASQUEZ |
| Reinforced Concrete Frame | 10/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 10/15/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/15/2020 | Partial Approval | JOE VELASQUEZ |
| Deputy Grading | 10/16/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 10/16/2020 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 10/30/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 10/30/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 11/4/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 11/5/2020 | Conditional Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 11/5/2020 | Partial Approval | JONATHAN QUACH |
| Structural Steel Frame | 11/13/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 11/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 11/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Insulation | 11/24/2020 | Approved | JOE VELASQUEZ |
| Wood Frame | 11/24/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 12/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 12/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 12/15/2020 | Approved | JOE VELASQUEZ |
| Final | 1/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/6/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 1/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 2/22/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 2/22/2021 | Approved | KENNETH ROBERTS |