11150 W ACAMA ST 91602
Certificate Information: 11150 W ACAMA ST 91602
- Application / Permit
- 18016-10000-28184
- Plan Check / Job No.
- B18LA18620
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL FOUR (N) ORDINERY MOMENT FRAMES
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/20/2020
Permit Application Status History
| Submitted | 8/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2018 | VARAND SARKISIAN |
| Corrections Issued | 10/23/2018 | VARAND SARKISIAN |
| Quality Review Completed | 10/23/2018 | SAI KHUM |
| Building Plans Picked Up | 10/31/2018 | APPLICANT |
| Plan Check Approved | 1/4/2019 | VARAND SARKISIAN |
| Issued | 1/14/2020 | LADBS |
| OK for CofC | 10/20/2020 | MARK FERRARI |
| CofC Issued | 10/20/2020 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/14/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Samama,, Albert; Lic. No.: C43288 | 22487 LIBERTY BELL RD CALABASAS, CA 91302 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/30/2020 | Partial Inspection | FRED WOHLFARTH |
| Special/Order Compliance | 1/30/2020 | Corrections Issued | FRED WOHLFARTH |
| Wood Frame | 3/4/2020 | Partial Approval | FRED WOHLFARTH |
| Deputy Drilled-In Anchors | 3/9/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Drilled-In Anchors | 5/13/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 5/18/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 5/19/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 5/22/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/22/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 5/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/26/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/26/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/26/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Insulation | 5/27/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/5/2020 | Approved | JOE VELASQUEZ |
| Final | 7/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/1/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 10/20/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 10/20/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 10/20/2020 | Approved | MARK FERRARI |