3121 S BAGLEY AVE 90034
Certificate Information: 3121 S BAGLEY AVE 90034
- Application / Permit
- 18016-10000-28013
- Plan Check / Job No.
- B18LA18457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL 2 (N) SPECIAL CANTILEVER COLUMN.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofC Issued on 3/21/2022
Permit Application Status History
| Submitted | 8/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2018 | VARAND SARKISIAN |
| Corrections Issued | 10/23/2018 | VARAND SARKISIAN |
| Quality Review Completed | 10/23/2018 | SAI KHUM |
| Building Plans Picked Up | 10/29/2018 | APPLICANT |
| Plan Check Approved | 11/6/2018 | VARAND SARKISIAN |
| Issued | 8/9/2021 | APPLICANT |
| OK for CofC | 3/16/2022 | GRANT WOODS |
| CofC Issued | 3/21/2022 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/1/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Ariel Muller; Lic. No.: 1026822-B | 525 N FULLER AVE LOS ANGELES, CA 90036 |
| Engineer | Senthil, Pulyadi; Lic. No.: C71630 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2021 | Corrections Issued | SORIN CIRSTOIU |
| Pre-Inspection | 8/12/2021 | Not Ready for Inspection | GRANT WOODS |
| Pre-Inspection | 9/30/2021 | Partial Inspection | GRANT WOODS |
| Deputy Reinf. Concrete | 11/2/2021 | Approved | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 11/2/2021 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 2/4/2022 | Conditional Approval | GRANT WOODS |
| Wood Frame | 2/11/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 2/17/2022 | Partial Approval | JOHN DODGE |
| Deputy Wood Construction | 2/18/2022 | Approved | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Approved | GRANT WOODS |
| Wood Frame | 2/18/2022 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 2/23/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 2/24/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 2/25/2022 | Approved | TIMOTHY BUXTON |
| Final | 3/16/2022 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 3/16/2022 | Approved | GRANT WOODS |