14227 W GILMORE ST 91401
Certificate Information: 14227 W GILMORE ST 91401
- Application / Permit
- 18016-10000-27966
- Plan Check / Job No.
- B18LA18408
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (3) STEEL SPECIAL CANTILEVER COLUMNS TO EXISTING 3-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/18/2022
Permit Application Status History
| Submitted | 8/29/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | ERIC WONG |
| Corrections Issued | 10/16/2018 | ERIC WONG |
| Quality Review Completed | 10/19/2018 | SAI KHUM |
| Building Plans Picked Up | 10/23/2018 | APPLICANT |
| Plan Check Approved | 2/6/2019 | ERIC WONG |
| Issued | 1/10/2020 | LADBS |
| OK for CofC | 4/18/2022 | WINSTON DUNNING |
| CofC Issued | 4/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/28/2019 | JOSE ROMERO-NAVARRO |
| Housing rent stabilization | Cleared | 10/17/2019 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Cedar Construction & Development Inc; Lic. No.: 554550-B | 10234 NATIONAL BLVD #1 LOS ANGELES, CA 90034 |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1730 E HOLLY AVE STE 107 EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2020 | Approved | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 2/4/2020 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 2/7/2020 | Conditional Approval | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Corrections Issued | FRED WOHLFARTH |
| Footing/Foundation/Slab | 3/18/2020 | Not Ready for Inspection | FRED WOHLFARTH |
| Structural Steel Frame | 3/18/2020 | Not Ready for Inspection | FRED WOHLFARTH |
| Wood Frame | 3/18/2020 | Not Ready for Inspection | FRED WOHLFARTH |
| Deputy Reinf. Concrete | 3/19/2020 | Partial Approval | FELIX CEBALLOS |
| Structural Steel Frame | 6/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 8/6/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/6/2020 | Partial Approval | JOE VELASQUEZ |
| Insulation | 8/11/2020 | Approved | VAHE KELEDJIAN |
| Structural Steel Frame | 8/12/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 8/13/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/17/2020 | Approved | JOE VELASQUEZ |
| Final | 9/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 2/25/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/25/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 4/18/2022 | OK for CofC | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | WINSTON DUNNING |
| Smoke Detectors | 4/18/2022 | Approved | WINSTON DUNNING |