12034 W KLING ST 91607
Certificate Information: 12034 W KLING ST 91607
- Application / Permit
- 18016-10000-27730
- Plan Check / Job No.
- B18LA18215
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL STEEL CANTILEVERED COLUMNS WITH GRADE BEAM
- Permit Issued
- Issued on 4/16/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/9/2020
Permit Application Status History
| Submitted | 8/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2018 | HANS SANTIAGO |
| Corrections Issued | 10/1/2018 | HANS SANTIAGO |
| Quality Review Completed | 10/2/2018 | JAMESON LEE |
| Building Plans Picked Up | 10/4/2018 | APPLICANT |
| Plan Check Approved | 10/24/2018 | Andrew Santiago |
| Issued | 4/16/2020 | LADBS |
| OK for CofC | 12/9/2020 | ERNESTO CORRAL |
| CofC Issued | 12/9/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/8/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Weinstein Construction Corporation; Lic. No.: 630439-B | 15102 RAYMER STREET VAN NUYS, CA 91405 |
| Engineer | Labib, Youhanna; Lic. No.: S4549 | 319 MAIN ST EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/7/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Other (see comments) | 6/3/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 6/8/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 6/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 6/15/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 6/25/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/26/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/26/2020 | Partial Approval | JOE VELASQUEZ |
| Insulation | 6/30/2020 | Approved | JOE VELASQUEZ |
| Final | 8/19/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 8/19/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/20/2020 | Approved | JOE VELASQUEZ |
| Final | 9/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/4/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 12/9/2020 | OK for CofC | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Approved | ERNESTO CORRAL |
| Smoke Detectors | 12/9/2020 | Approved | ERNESTO CORRAL |