1861 S MIDVALE AVE 90025
Certificate Information: 1861 S MIDVALE AVE 90025
- Application / Permit
- 18016-10000-27583
- Plan Check / Job No.
- B18LA18105
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/23/2020
Permit Application Status History
| Submitted | 8/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | MANUEL MONTUFAR |
| Corrections Issued | 10/16/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 10/17/2018 | SAI KHUM |
| Building Plans Picked Up | 10/19/2018 | APPLICANT |
| Plan Check Approved | 10/24/2018 | MANUEL MONTUFAR |
| Issued | 1/23/2020 | LADBS |
| OK for CofC | 4/16/2020 | GRANT WOODS |
| CofC Issued | 4/23/2020 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/14/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Zenith, Engineers; Lic. No.: C71630 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2020 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 2/18/2020 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 2/20/2020 | Partial Approval | DERRICK SPENCER |
| Structural Steel Frame | 2/20/2020 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 2/20/2020 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/21/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 3/2/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 3/25/2020 | Approved | TED RIES |
| Structural Steel Frame | 3/25/2020 | Approved | TED RIES |
| Wood Frame | 3/25/2020 | Approved | TED RIES |
| Interior/Exterior Lathing | 4/2/2020 | Approved | PAUL DAVIDSON |
| Final | 4/16/2020 | OK for CofC | GRANT WOODS |
| METHANE-Final | 4/16/2020 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 4/16/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 4/16/2020 | Approved | GRANT WOODS |