15 E 18TH AVE 90291
Certificate Information: 15 E 18TH AVE 90291
- Application / Permit
- 18016-10000-27355
- Plan Check / Job No.
- B18LA17933
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (2) STEEL SPECIAL CANTILEVER COLUMNS AND WOOD SHEAR WALLS TO EXISTING 3-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 4/17/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 5/19/2021
Permit Application Status History
| Submitted | 8/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2018 | ERIC WONG |
| Corrections Issued | 9/24/2018 | ERIC WONG |
| Quality Review Completed | 9/28/2018 | SAI KHUM |
| Building Plans Picked Up | 10/4/2018 | APPLICANT |
| Plan Check Approved | 11/28/2018 | ERIC WONG |
| Issued | 4/17/2020 | LADBS |
| OK for CofC | 5/19/2021 | GRANT WOODS |
| CofC Issued | 5/19/2021 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/15/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 1626 S MAYFLOWER AVE UNIT B MONROVIA, CA 91016 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2020 | Approved | SORIN CIRSTOIU |
| Wood Frame | 6/11/2020 | Partial Approval | SORIN CIRSTOIU |
| Deputy Wood Construction | 6/17/2020 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Other (see comments) | 6/18/2020 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 6/18/2020 | Approved | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2020 | Approved | SORIN CIRSTOIU |
| Wood Frame | 6/18/2020 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 9/28/2020 | Partial Approval | GRANT WOODS |
| Final | 12/10/2020 | Partial Approval | SORIN CIRSTOIU |
| METHANE-Final | 12/10/2020 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 12/10/2020 | Approved | SORIN CIRSTOIU |
| Final | 5/19/2021 | OK for CofC | GRANT WOODS |