428 S HAMEL ROAD 90048

Certificate Information: 428 S HAMEL ROAD 90048

Application / Permit
18016-10000-27318
Plan Check / Job No.
B18LA18209
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
E-plan 288::SOFT-STORY SEISMIC RETROFIT PER LABC CHAPTER. 93: Soft story retrofit using moment frame at front elevation
Permit Issued
Issued on 2/13/2020
Issuing Office
Metro
Current Status
CofC Issued on 1/14/2021

Permit Application Status History

Submitted 8/28/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 DANIEL SANJUAN
Corrections Issued 10/11/2018 DANIEL SANJUAN
Quality Review Completed 10/12/2018 CELESTE MORRIS
Plan Check Approved 1/24/2019 DANIEL SANJUAN
Issued 2/13/2020 LADBS
OK for CofC 1/11/2021 MARK FERRARI
CofC Issued 1/14/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 1/8/2020 ISMAEL HERNANDEZ

Contact Information

Architect Louis, Marinelli; Lic. No.: C29680       ,
Contractor Rigid Design & Construction Inc; Lic. No.: 947498-B 14813 MORRISON ST      SHERMAN OAKS, CA 91403

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/18/2020 Approved DARRYL ARNOLD
Deputy Steel/Welding 7/1/2020 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 7/9/2020 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/9/2020 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 7/13/2020 Partial Approval DARRYL ARNOLD
Deputy Steel/Welding 9/16/2020 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 10/7/2020 Approved JONATHAN QUACH
Wood Frame 10/7/2020 Approved JONATHAN QUACH
Interior/Exterior Lathing 10/14/2020 Approved JONATHAN QUACH
Final 10/28/2020 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Not Ready DARRYL ARNOLD
Final 12/30/2020 Conditional Approval JONATHAN QUACH
METHANE-Final 12/30/2020 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 12/30/2020 SGSOV Approved JONATHAN QUACH
Smoke Detectors 12/30/2020 Approved JONATHAN QUACH
Final 1/11/2021 OK for CofC MARK FERRARI