11415 1/2 W CHENAULT ST 90049

Certificate Information: 11415 1/2 W CHENAULT ST 90049

Application / Permit
18016-10000-27106
Plan Check / Job No.
B18LA17664
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 8/24/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 MICHAEL LOPEZ
Corrections Issued 8/23/2018 MICHAEL LOPEZ
Applicant returned to address corrections 8/24/2018 KEVIN MORALES
Plan Check Approved 8/24/2018 AUNG SOE
Issued 8/24/2018 LADBS
CofO in Progress 3/11/2020 CARLOS MATAMOROS
Permit Finaled 3/18/2020 VINCENT COTTON
CofO Issued 3/18/2020 VINCENT COTTON
Permit Finaled 3/18/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 8/23/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 8/23/2018 MICHAEL CASTILLO
Grading Pre-Inspection Cleared 8/23/2018 BARTON HOLMES
Sewer availability Cleared 8/23/2018 MICHAEL CASTILLO
Specific Plan Cleared 8/23/2018 EDER ROMERO
Low Impact Development Cleared 8/24/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/24/2018 CELINA MORENO

Contact Information

Contractor Stevens Mark Construction Co Inc; Lic. No.: 681686-B 19420 SANTA RITA STREET      TARZANA, CA 91356
Engineer Sayah, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/20/2019 Corrections Issued ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 2/26/2019 Approved ANTHONY MCDOWALL
Footing/Foundation/Slab 2/26/2019 Approved ANTHONY MCDOWALL
Sewer 3/21/2019 Approved ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 5/1/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 5/7/2019 Approved ANTHONY MCDOWALL
ELECTRICAL-Rough 5/13/2019 Corrections Issued ANTHONY MCDOWALL
ELECTRICAL-Rough 5/16/2019 Approved ANTHONY MCDOWALL
BUILDING-Rough-Frame 6/4/2019 Approved ANTHONY MCDOWALL
MERV13>=Rough 6/4/2019 Approved ANTHONY MCDOWALL
METHANE-Rough 6/4/2019 Approved ANTHONY MCDOWALL
Insulation 6/14/2019 Not Ready for Inspection ANTHONY MCDOWALL
Interior/Exterior Lathing 6/24/2019 Partial Approval ANTHONY MCDOWALL
Insulation 6/28/2019 Approved ANTHONY MCDOWALL
Drywall Nailing 7/3/2019 Approved ANTHONY MCDOWALL
Shower Pan 8/27/2019 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 9/3/2019 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 12/31/2019 Approved ANTHONY MCDOWALL
PLUMBING-Final 1/3/2020 Approved ANTHONY MCDOWALL
HVAC-Final 1/15/2020 Not Ready for Inspection CARLOS MATAMOROS
Final 1/27/2020 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Final 1/27/2020 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/27/2020 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 1/27/2020 Approved CARLOS MATAMOROS
HVAC-Final 1/30/2020 Corrections Issued CARLOS MATAMOROS
Final 2/6/2020 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 3/3/2020 Approved CARLOS MATAMOROS
Green Building Final 3/3/2020 Approved CARLOS MATAMOROS
HVAC-Final 3/3/2020 Approved CARLOS MATAMOROS
Service/Power Release 3/3/2020 Approved CARLOS MATAMOROS
Final 3/11/2020 OK to Issue CofO CARLOS MATAMOROS