11415 1/2 W CHENAULT ST 90049
Certificate Information: 11415 1/2 W CHENAULT ST 90049
- Application / Permit
- 18016-10000-27106
- Plan Check / Job No.
- B18LA17664
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 8/24/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | MICHAEL LOPEZ |
| Corrections Issued | 8/23/2018 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/24/2018 | KEVIN MORALES |
| Plan Check Approved | 8/24/2018 | AUNG SOE |
| Issued | 8/24/2018 | LADBS |
| CofO in Progress | 3/11/2020 | CARLOS MATAMOROS |
| Permit Finaled | 3/18/2020 | VINCENT COTTON |
| CofO Issued | 3/18/2020 | VINCENT COTTON |
| Permit Finaled | 3/18/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2018 | MICHAEL CASTILLO |
| Grading Pre-Inspection | Cleared | 8/23/2018 | BARTON HOLMES |
| Sewer availability | Cleared | 8/23/2018 | MICHAEL CASTILLO |
| Specific Plan | Cleared | 8/23/2018 | EDER ROMERO |
| Low Impact Development | Cleared | 8/24/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/24/2018 | CELINA MORENO |
Contact Information
| Contractor | Stevens Mark Construction Co Inc; Lic. No.: 681686-B | 19420 SANTA RITA STREET TARZANA, CA 91356 |
| Engineer | Sayah, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/20/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 2/26/2019 | Approved | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/26/2019 | Approved | ANTHONY MCDOWALL |
| Sewer | 3/21/2019 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2019 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 5/7/2019 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 5/13/2019 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 5/16/2019 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 6/4/2019 | Approved | ANTHONY MCDOWALL |
| MERV13>=Rough | 6/4/2019 | Approved | ANTHONY MCDOWALL |
| METHANE-Rough | 6/4/2019 | Approved | ANTHONY MCDOWALL |
| Insulation | 6/14/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 6/24/2019 | Partial Approval | ANTHONY MCDOWALL |
| Insulation | 6/28/2019 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 7/3/2019 | Approved | ANTHONY MCDOWALL |
| Shower Pan | 8/27/2019 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 9/3/2019 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 12/31/2019 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Final | 1/3/2020 | Approved | ANTHONY MCDOWALL |
| HVAC-Final | 1/15/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 1/27/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 1/27/2020 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2020 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 1/27/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/30/2020 | Corrections Issued | CARLOS MATAMOROS |
| Final | 2/6/2020 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/3/2020 | Approved | CARLOS MATAMOROS |
| Green Building Final | 3/3/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 3/3/2020 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 3/3/2020 | Approved | CARLOS MATAMOROS |
| Final | 3/11/2020 | OK to Issue CofO | CARLOS MATAMOROS |