221 S PARK VIEW ST 90057
Certificate Information: 221 S PARK VIEW ST 90057
- Application / Permit
- 18016-10000-27103
- Plan Check / Job No.
- B18LA17661
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL 2 (N) SPECIAL CANTILEVER COLUMNS
- Permit Issued
- Issued on 4/16/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 5/5/2021
Permit Application Status History
| Submitted | 8/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 10/15/2018 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 10/17/2018 | SAI KHUM |
| Building Plans Picked Up | 12/6/2018 | APPLICANT |
| Plan Check Approved | 12/13/2018 | TEODORO DIAZ RODRIGUEZ |
| No Progress | 4/9/2020 | JESSE VIDUYA |
| Plan Check Approved | 4/16/2020 | DOMINIQUE HAAS |
| Issued | 4/16/2020 | LADBS |
| OK for CofC | 4/28/2021 | MARK FERRARI |
| CofC Issued | 5/5/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/3/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Ces4 Construction; Lic. No.: 1042127-B | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/11/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/17/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 6/23/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 6/23/2020 | Approved | MARK FERRARI |
| Wood Frame | 6/23/2020 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 7/2/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/2/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/7/2020 | Approved | DARRYL ARNOLD |
| Final | 7/17/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 7/17/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/17/2020 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 7/17/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 7/21/2020 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Final | 7/21/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/21/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 7/21/2020 | Approved | DARRYL ARNOLD |
| Final | 4/28/2021 | OK for CofC | MARK FERRARI |