1656 S ARLINGTON AVE 90019
Certificate Information: 1656 S ARLINGTON AVE 90019
- Application / Permit
- 18016-10000-26978
- Plan Check / Job No.
- B18LA17583
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) STEEL CANTILEVERED COLUMN
- Permit Issued
- Issued on 4/23/2020
- Issuing Office
- Metro
- Current Status
- OK for CofC on 7/24/2020
Permit Application Status History
| Submitted | 8/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | HANS SANTIAGO |
| Corrections Issued | 9/17/2018 | HANS SANTIAGO |
| Quality Review Completed | 9/18/2018 | SAI KHUM |
| Building Plans Picked Up | 9/21/2018 | APPLICANT |
| Applicant returned to address corrections | 11/5/2018 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/11/2019 | HANS SANTIAGO |
| Plan Check Approved | 11/5/2019 | ANDREW SANTIAGO |
| Plan Check Approved | 12/10/2019 | ANDREW SANTIAGO |
| Issued | 4/23/2020 | LADBS |
| OK for CofC | 7/20/2020 | DARRYL ARNOLD |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 11/25/2019 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 11/25/2019 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 12/6/2019 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 12/6/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2019 | PAMELA TENEZA |
| Housing rent stabilization | Cleared | 4/14/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Bh Construction Co; Lic. No.: 553541-B | 9701 WEST PICO BOULEVARD # 209 LOS ANGELES, CA 90035 |
| Engineer | Martirossyan, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2020 | Approved | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 5/11/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/14/2020 | Approved | DARRYL ARNOLD |
| Insulation | 5/18/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/18/2020 | Approved | DARRYL ARNOLD |
| Final | 5/20/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/20/2020 | Approved | DARRYL ARNOLD |
| METHANE-Final | 5/20/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/20/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/20/2020 | Approved | DARRYL ARNOLD |
| Final | 7/20/2020 | OK for CofC | DARRYL ARNOLD |
| Special/Order Compliance | 11/6/2024 | Corrections Issued | DARRYL ARNOLD |