5110 E O'SULLIVAN DR 90032
Certificate Information: 5110 E O'SULLIVAN DR 90032
- Application / Permit
- 18016-10000-26638
- Plan Check / Job No.
- B18LA17379
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. COMPLY WITH DEPARTMENT ORDER effective date 04/26/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2018 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/17/2018 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/10/2019 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/11/2019 | JESSE JIMENEZ |
| Plan Check Approved | 12/11/2019 | KEVIN MORALES |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 12/7/2021 | COREY HUPP |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2018 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 9/6/2018 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 9/6/2018 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 9/6/2018 | CELINA MORENO |
| Sewer availability | Cleared | 9/6/2018 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 7/10/2019 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 7/10/2019 | JEANIE LAM |
| "D" conditions | Cleared | 9/26/2019 | DIANA JIMENEZ |
| "Q" conditions | Cleared | 9/26/2019 | DIANA JIMENEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2019 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2020 | Conditional Approval | ALFREDO BALANDRA |
| ELECTRICAL-Rough | 3/3/2020 | Not Ready for Inspection | ALFREDO BALANDRA |
| PLUMBING-Rough | 3/3/2020 | Not Ready for Inspection | ALFREDO BALANDRA |
| ELECTRICAL-Rough | 3/12/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/12/2020 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/27/2020 | Partial Approval | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/30/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/1/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/1/2020 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 5/1/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 5/5/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/7/2020 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/19/2020 | Approved | ENRIQUE MIRELES |
| Sewer | 5/19/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/19/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/27/2020 | Approved | ENRIQUE MIRELES |
| Final | 5/27/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 5/27/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/27/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/27/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 5/27/2020 | Approved | ENRIQUE MIRELES |
| Final | 6/25/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 6/23/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 11/3/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 12/6/2021 | OK to Issue CofO | COREY HUPP |