1243 N VIRGIL AVE 90029
Certificate Information: 1243 N VIRGIL AVE 90029
- Application / Permit
- 18016-10000-26211
- Plan Check / Job No.
- B18LA17078
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH. 93. INSTALL STEEL MOMENT FRAME AND STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- CofC Issued on 7/26/2021
Permit Application Status History
| Submitted | 8/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | MANUEL MONTUFAR |
| Corrections Issued | 9/18/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 9/19/2018 | SAI KHUM |
| Building Plans Picked Up | 9/20/2018 | APPLICANT |
| Plan Check Approved | 10/11/2018 | MANUEL MONTUFAR |
| Issued | 10/29/2020 | APPLICANT |
| OK for CofC | 7/26/2021 | BRUCE CAMPBELL |
| OK to Issue CofC | 7/26/2021 | WINSTON DUNNING |
| CofC Issued | 7/26/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/18/2020 | MICHAEL SOTO |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | American, Retrofitters.; Lic. No.: C86987 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2021 | Corrections Issued | JONATHAN QUACH |
| Wood Frame | 3/11/2021 | Partial Inspection | JONATHAN QUACH |
| Deputy Steel/Welding | 3/17/2021 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 3/30/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 3/30/2021 | Approved | MARK FERRARI |
| Wood Frame | 3/30/2021 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 3/31/2021 | Conditional Approval | FRED WOHLFARTH |
| Interior/Exterior Lathing | 4/16/2021 | Approved | MARK FERRARI |
| Final | 5/18/2021 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 5/18/2021 | Approved | MARK FERRARI |
| Final | 7/26/2021 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 7/26/2021 | SGSOV Approved | BRUCE CAMPBELL |