1257 S CITRUS AVE 90019

Certificate Information: 1257 S CITRUS AVE 90019

Application / Permit
18016-10000-25984
Plan Check / Job No.
B18LA16924
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (2) STEEL SPECIAL CANTILEVER COLUMNS TO EXISTING 2-STORY APARTMENT BUILDING
Permit Issued
Issued on 2/19/2020
Issuing Office
Metro
Current Status
CofC Issued on 10/14/2020

Permit Application Status History

Submitted 8/13/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 RICARDO SUPAN
Corrections Issued 9/10/2018 RICARDO SUPAN
Quality Review Completed 9/12/2018 SAI KHUM
Building Plans Picked Up 9/18/2018 APPLICANT
Applicant returned to address corrections 10/3/2018 RICARDO SUPAN
Plan Check Approved 11/1/2018 RICARDO SUPAN
Issued 2/19/2020 LADBS
OK for CofC 10/5/2020 ERNESTO CORRAL
CofC Issued 10/14/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 2/18/2020 MICHAEL SOTO

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Erich, Jason Axsom; Lic. No.: S4435 92 CORPORATE PARK   C125    IRVINE, CA 92606

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2020 Approved DARRYL ARNOLD
Wood Frame 3/16/2020 Approved DARRYL ARNOLD
Wood Frame 3/18/2020 Partial Approval TIMOTHY BUXTON
Deputy Wood Construction 3/19/2020 Partial Approval DARRYL ARNOLD
Deputy Steel/Welding 3/23/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 3/24/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/24/2020 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 3/25/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 4/24/2020 Approved DARRYL ARNOLD
Final 8/31/2020 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV Not Ready DARRYL ARNOLD
Final 9/21/2020 Conditional Approval FELIX CEBALLOS
METHANE-Final 9/21/2020 Approved FELIX CEBALLOS
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Approved FELIX CEBALLOS
Smoke Detectors 9/21/2020 Approved FELIX CEBALLOS
Final 10/5/2020 OK for CofC ERNESTO CORRAL