5465 W ALVERN CIR 90045

Certificate Information: 5465 W ALVERN CIR 90045

Application / Permit
18016-10000-25934
Plan Check / Job No.
B18LA16881
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (1) STEEL SPECIAL CANTILEVER COLUMN TO EXISTING 2-STORY APARTMENT BUILDING
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofC Issued on 6/11/2025

Permit Application Status History

Submitted 8/13/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 RICARDO SUPAN
Corrections Issued 9/10/2018 RICARDO SUPAN
Quality Review Completed 9/11/2018 SAI KHUM
Building Plans Picked Up 9/21/2018 APPLICANT
Plan Check Approved 8/24/2022 JESSE VIDUYA
Issued 10/14/2022 APPLICANT
OK for CofC 6/4/2025 PAUL DAVIDSON
CofC Issued 6/11/2025 DAVID TSAU

Permit Application Clearance Information

Housing rent stabilization Cleared 9/9/2022 RICARDO BOHORQUEZ

Contact Information

Contractor A M A Construction Services Inc; Lic. No.: 831856-B 536 W ARROW HWY SUITE 201      COVINA, CA 91722
Engineer Elmustapha,, Ahmad; Lic. No.: C49021 1608 CALLE CRISTINA      SAN DIMAS, CA 91773

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/23/2024 Partial Approval RICARDO ROBLES
Pre-Inspection 2/11/2025 Approved RICARDO ROBLES
Deputy Drilled-In Anchors 2/18/2025 Conditional Approval RICARDO ROBLES
Deputy Steel/Welding 2/18/2025 Conditional Approval RICARDO ROBLES
Deputy Reinf. Concrete 2/19/2025 Conditional Approval RICARDO ROBLES
Deputy Drilled-In Anchors 2/20/2025 Conditional Approval MICHAEL PETRUSKO
Excavation/Setback/Form/Re-Bar 2/20/2025 Approved MICHAEL PETRUSKO
Structural Steel Frame 2/20/2025 Approved MICHAEL PETRUSKO
Wood Frame 2/20/2025 Approved MICHAEL PETRUSKO
Deputy Reinf. Concrete 2/24/2025 Conditional Approval RICARDO ROBLES
Interior/Exterior Lathing 3/13/2025 Partial Approval RICARDO ROBLES
Final 5/30/2025 Not Ready for Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 5/30/2025 Not Ready for Inspection PAUL DAVIDSON
Final 6/4/2025 OK for CofC PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 6/4/2025 Approved PAUL DAVIDSON