6658 N WILKINSON AVE 91606
Certificate Information: 6658 N WILKINSON AVE 91606
- Application / Permit
- 18016-10000-25704
- Plan Check / Job No.
- B18LA16725
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (N) STEEL CANTILEVERED COLUMN
- Permit Issued
- Issued on 3/30/2021
- Issuing Office
- Current Status
- CofC Issued on 12/9/2021
Permit Application Status History
| Submitted | 8/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2018 | HANS SANTIAGO |
| Corrections Issued | 10/2/2018 | HANS SANTIAGO |
| Quality Review Completed | 10/4/2018 | JAMESON LEE |
| Building Plans Picked Up | 10/11/2018 | APPLICANT |
| Applicant returned to address corrections | 12/19/2018 | HANS SANTIAGO |
| Plan Check Approved | 12/31/2018 | Andrew Santiago |
| Issued | 3/30/2021 | APPLICANT |
| OK for CofC | 10/21/2021 | KENNETH ROBERTS |
| CofC Issued | 12/9/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/25/2021 | MICHAEL SOTO |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 8730 COSTA VERDE BLVD APT 2348 SAN DIEGO, CA 92122 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 5/7/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/7/2021 | Approved | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/12/2021 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/14/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/17/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 5/18/2021 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/19/2021 | No Access for Inspection | JOE VELASQUEZ |
| Insulation | 7/21/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 7/21/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/17/2021 | Approved | JOE VELASQUEZ |
| Final | 9/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 10/21/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/21/2021 | Approved | KENNETH ROBERTS |