4866 W VENICE BLVD 90019
Certificate Information: 4866 W VENICE BLVD 90019
- Application / Permit
- 18016-10000-25482
- Plan Check / Job No.
- B18LA16546
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING STEEL CANTILEVERED COLUMNS
- Permit Issued
- Issued on 8/30/2024
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/13/2024
Permit Application Status History
| Submitted | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2018 | HANS SANTIAGO |
| Corrections Issued | 9/25/2018 | HANS SANTIAGO |
| Quality Review Completed | 9/28/2018 | SAI KHUM |
| Building Plans Picked Up | 10/24/2018 | APPLICANT |
| Plan Check Approved | 12/6/2018 | Andrew Santiago |
| Issued | 8/30/2024 | APPLICANT |
| OK for CofC | 12/13/2024 | WINSTON DUNNING |
| CofC Issued | 12/13/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/29/2024 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 2523 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Acciani, Mark; Lic. No.: C83929 | P.O. BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2024 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/10/2024 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 10/10/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/10/2024 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 10/17/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/17/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/21/2024 | Approved | DARRYL ARNOLD |
| Final | 10/31/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 10/31/2024 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/31/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/31/2024 | Approved | DARRYL ARNOLD |
| Final | 12/13/2024 | OK for CofC | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Approved | WINSTON DUNNING |