1442 N LUCILE AVE 90026
Certificate Information: 1442 N LUCILE AVE 90026
- Application / Permit
- 18016-10000-24821
- Plan Check / Job No.
- B18LA16111
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (N) ORDINERY MOMENT FRAME
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofC Issued on 12/16/2020
Permit Application Status History
| Submitted | 8/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | VARAND SARKISIAN |
| Corrections Issued | 9/20/2018 | VARAND SARKISIAN |
| Quality Review Completed | 9/21/2018 | SAI KHUM |
| Building Plans Picked Up | 9/24/2018 | APPLICANT |
| Plan Check Approved | 10/16/2018 | VARAND SARKISIAN |
| Issued | 6/3/2020 | APPLICANT |
| OK for CofC | 12/14/2020 | MARK FERRARI |
| CofC Issued | 12/16/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/14/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/9/2020 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Steel/Welding | 6/12/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 6/22/2020 | Partial Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 6/24/2020 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 6/30/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 7/1/2020 | Conditional Approval | VAHE KELEDJIAN |
| Structural Steel Frame | 7/7/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/7/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/10/2020 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 7/28/2020 | SGSOV Approved | MARK FERRARI |
| Final | 10/15/2020 | Corrections Issued | MARK FERRARI |
| Smoke Detectors | 10/15/2020 | Approved | MARK FERRARI |
| Final | 12/14/2020 | OK for CofC | MARK FERRARI |