470 S MARIPOSA AVE 90020

Certificate Information: 470 S MARIPOSA AVE 90020

Application / Permit
18016-10000-24743
Plan Check / Job No.
B18LA16051
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LAMC DIVISION 93. RETROFIT CONSISTS OF INSTALLING (1) NEW 2-BAY ORDINARY MOMENT FRAME TO EXISTING 3-STORY APARTMENT BUILDING
Permit Issued
Issued on 4/13/2020
Issuing Office
Current Status
CofC Issued on 2/2/2021

Permit Application Status History

Submitted 8/2/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 RICARDO SUPAN
Corrections Issued 9/4/2018 RICARDO SUPAN
Quality Review Completed 9/5/2018 SAI KHUM
Building Plans Picked Up 9/13/2018 APPLICANT
Applicant returned to address corrections 11/1/2018 RICARDO SUPAN
Plan Check Approved 11/1/2018 RICARDO SUPAN
Issued 4/13/2020 APPLICANT
OK for CofC 1/19/2021 JONATHAN QUACH
CofC Issued 2/2/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 3/26/2020 PHILLIP MUNGUIA

Contact Information

Contractor Par Construction Inc; Lic. No.: 983593-B 12319 GREENE AVE      LOS ANGELES, CA 90066
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2020 Approved MARK FERRARI
Deputy Steel/Welding 10/5/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 10/7/2020 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 10/14/2020 Approved MARK FERRARI
Footing/Foundation/Slab 10/14/2020 Approved MARK FERRARI
Structural Steel Frame 10/14/2020 Partial Approval MARK FERRARI
Wood Frame 10/14/2020 Not Ready for Inspection MARK FERRARI
Deputy Reinf. Concrete 10/16/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 10/27/2020 Conditional Approval MARK FERRARI
Structural Steel Frame 10/29/2020 Approved SABAS ALONSO
Wood Frame 10/29/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 11/12/2020 Corrections Issued MARK FERRARI
Interior/Exterior Lathing 11/19/2020 Approved MARK FERRARI
Final 12/21/2020 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 12/21/2020 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 12/21/2020 Not Ready for Inspection DARRYL ARNOLD
Final 1/19/2021 OK for CofC JONATHAN QUACH
METHANE-Final 1/19/2021 Approved JONATHAN QUACH
Smoke Detectors 1/19/2021 Approved JONATHAN QUACH