11920 W CHANDLER BLVD 91607
Certificate Information: 11920 W CHANDLER BLVD 91607
- Application / Permit
- 18016-10000-24734
- Plan Check / Job No.
- B18LA16042
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER DIVISION 93. RETROFIT CONSISTS OF INSTALLING (6) STEEL SPECIAL CANTILEVER COLUMNS TO EXISTING 2-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/15/2021
Permit Application Status History
| Submitted | 8/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | ERIC WONG |
| Corrections Issued | 9/5/2018 | ERIC WONG |
| Quality Review Completed | 9/6/2018 | SAI KHUM |
| Building Plans Picked Up | 9/13/2018 | APPLICANT |
| Applicant returned to address corrections | 9/25/2018 | ERIC WONG |
| Plan Check Approved | 10/31/2018 | ERIC WONG |
| Issued | 1/28/2020 | LADBS |
| OK for CofC | 12/2/2021 | KENNETH ROBERTS |
| CofC Issued | 12/15/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 9/25/2018 | SAI KHUM |
| Housing rent stabilization | Cleared | 1/13/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2020 | Corrections Issued | FRED WOHLFARTH |
| Deputy Other (see comments) | 5/27/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 5/28/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 5/28/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/28/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 6/4/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 6/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/17/2020 | Partial Approval | JOE VELASQUEZ |
| Insulation | 6/19/2020 | Approved | JOE VELASQUEZ |
| Deputy Steel/Welding | 6/22/2020 | No Access for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/26/2020 | Approved | JOE VELASQUEZ |
| Final | 12/2/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 12/2/2021 | Approved | KENNETH ROBERTS |