5330 W FRANKLIN AVE 90027
Certificate Information: 5330 W FRANKLIN AVE 90027
- Application / Permit
- 18016-10000-24667
- Plan Check / Job No.
- B18LA15993
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 USING STEEL MOMENT FRAME AND HARDY FRAME PANELS.
- Permit Issued
- Issued on 3/31/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 9/17/2020
Permit Application Status History
| Submitted | 8/1/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | HANS SANTIAGO |
| Corrections Issued | 9/18/2018 | HANS SANTIAGO |
| Quality Review Completed | 9/21/2018 | SAI KHUM |
| Building Plans Picked Up | 9/25/2018 | APPLICANT |
| Applicant returned to address corrections | 12/31/2018 | HANS SANTIAGO |
| Plan Check Approved | 1/29/2019 | Andrew Santiago |
| Issued | 3/31/2020 | LADBS |
| OK for CofC | 5/20/2020 | FELIX CEBALLOS |
| CofC Issued | 9/17/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/26/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Encon Technologies Inc; Lic. No.: 748576-A | 12145 MORA DRIVE SUITE #7 SANTA FE SPRINGS, CA 90670 |
| Engineer | , ; Lic. No.: C84617 | 19900 ACRE ST LOS ANGELES, CA 91324 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2020 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 4/13/2020 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 4/23/2020 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 4/27/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 4/28/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 4/30/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 4/30/2020 | Partial Approval | MARK FERRARI |
| Structural Steel Frame | 5/4/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 5/4/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 5/8/2020 | Approved | MARK FERRARI |
| Final | 5/15/2020 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 5/15/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 5/15/2020 | Approved | MARK FERRARI |
| Final | 5/20/2020 | Conditional Approval | FELIX CEBALLOS |
| Special/Order Compliance | 6/15/2020 | Corrections Issued | FELIX CEBALLOS |
| Special/Order Compliance | 6/24/2020 | Corrections Issued | MARK FERRARI |
| Special/Order Compliance | 9/11/2020 | Approved | MARK FERRARI |