17950 W BURBANK BLVD 91316

Certificate Information: 17950 W BURBANK BLVD 91316

Application / Permit
18016-10000-24579
Plan Check / Job No.
B18LA15932
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS, PLYWOOD SHEAR WALLS AND SIMPSON STRONG WALLS.
Permit Issued
Issued on 2/21/2020
Issuing Office
Metro
Current Status
CofC Issued on 10/20/2020

Permit Application Status History

Submitted 8/1/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 MANUEL MONTUFAR
Corrections Issued 9/5/2018 MANUEL MONTUFAR
Quality Review Completed 9/7/2018 SAI KHUM
Building Plans Picked Up 9/12/2018 APPLICANT
Plan Check Approved 7/23/2019 MANUEL MONTUFAR
Issued 2/21/2020 LADBS
OK for CofC 8/17/2020 DANIEL VARNUM
CofC Issued 10/20/2020 DAVID TSAU

Permit Application Clearance Information

Housing rent stabilization Cleared 2/20/2020 MICHAEL SOTO

Contact Information

Contractor Cal - Quake Construction Inc; Lic. No.: 759817-B 636 NORTH FORMOSA AVENUE      LOS ANGELES, CA 90036
Engineer Kumar, Jay Nevin; Lic. No.: C77601 3507 WEST 25TH STREET      LOS ANGELES, CA 90018

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2020 Partial Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval DANIEL VARNUM
Wood Frame 4/28/2020 Approved HAMID PISHEHVAR
Excavation/Setback/Form/Re-Bar 5/22/2020 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 5/22/2020 Approved HAMID PISHEHVAR
Deputy Drilled-In Anchors 5/26/2020 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 5/26/2020 Conditional Approval DANIEL VARNUM
Structural Steel Frame 6/3/2020 Not Ready for Inspection DANIEL VARNUM
Wood Frame 6/3/2020 Not Ready for Inspection DANIEL VARNUM
Structural Steel Frame 6/11/2020 Approved DANIEL VARNUM
Wood Frame 6/11/2020 Approved DANIEL VARNUM
Interior/Exterior Lathing 6/25/2020 Approved DANIEL VARNUM
Final 8/12/2020 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 8/12/2020 Not Ready for Inspection DANIEL VARNUM
Final 8/17/2020 OK for CofC DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Approved DANIEL VARNUM
Smoke Detectors 8/17/2020 Approved DANIEL VARNUM