- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAMES
- Permit Issued
- Issued on 6/28/2021
- Issuing Office
- Current Status
- CofC Issued on 10/4/2021
Permit Application Status History
| Submitted | 7/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | MANUEL MONTUFAR |
| Corrections Issued | 9/5/2018 | MANUEL MONTUFAR |
| Quality Review Completed | 9/6/2018 | SAI KHUM |
| Building Plans Picked Up | 9/11/2018 | APPLICANT |
| Plan Check Approved | 12/13/2018 | MANUEL MONTUFAR |
| Issued | 6/28/2021 | APPLICANT |
| OK for CofC | 9/30/2021 | JOHN DODGE |
| CofC Issued | 10/4/2021 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/19/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 8730 COSTA VERDE BLVD APT 2348 SAN DIEGO, CA 92122 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 7/2/2021 | Not Ready for Inspection | GRANT WOODS |
| Pre-Inspection | 7/6/2021 | Approved | JOHN DODGE |
| Deputy Steel/Welding | 7/7/2021 | Approved | JOHN DODGE |
| Deputy Steel/Welding | 7/8/2021 | Conditional Approval | JOHN DODGE |
| Wood Frame | 7/9/2021 | Partial Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/15/2021 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 7/15/2021 | Conditional Approval | JOHN DODGE |
| Insulation | 7/16/2021 | Partial Approval | JOHN DODGE |
| Structural Steel Frame | 7/16/2021 | Partial Approval | JOHN DODGE |
| Wood Frame | 7/16/2021 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 7/19/2021 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 7/20/2021 | Conditional Approval | JOHN DODGE |
| Wood Frame | 7/27/2021 | Partial Approval | JOHN DODGE |
| Deputy Wood Construction | 8/4/2021 | Conditional Approval | JOHN DODGE |
| Deputy Wood Construction | 8/10/2021 | Conditional Approval | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Not Ready for Inspection | JOHN DODGE |
| Deputy Steel/Welding | 8/23/2021 | Approved | JOHN DODGE |
| Insulation | 8/25/2021 | Approved | JOHN DODGE |
| Structural Steel Frame | 8/25/2021 | Approved | JOHN DODGE |
| Wood Frame | 8/25/2021 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 9/14/2021 | Approved | ALAN NOVAK |
| Final | 9/30/2021 | OK for CofC | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 9/30/2021 | Approved | JOHN DODGE |