6226 N CRANER AVE 91606
Certificate Information: 6226 N CRANER AVE 91606
- Application / Permit
- 18016-10000-24110
- Plan Check / Job No.
- B18LA15598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 3 (N) SCCS.
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofC Issued on 4/26/2021
Permit Application Status History
| Submitted | 7/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | GEORGE ALVAREZ |
| Corrections Issued | 9/10/2018 | GEORGE ALVAREZ |
| Quality Review Completed | 9/13/2018 | SAI KHUM |
| Building Plans Picked Up | 9/21/2018 | APPLICANT |
| Plan Check Approved | 2/19/2020 | GEORGE ALVAREZ |
| No Progress | 2/19/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 2/19/2020 | GEORGE ALVAREZ |
| Issued | 8/11/2020 | APPLICANT |
| OK for CofC | 3/22/2021 | KENNETH ROBERTS |
| CofC Issued | 4/26/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/4/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | 9751 WHEATLAND AVE SUNLAND, CA 91040 |
| Engineer | Biayna, Engineering & Construction; Lic. No.: S6232 | 9751 WHEATLAND AVE LOS ANGELES, CA 91040 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 9/10/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 9/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/16/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 12/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/10/2020 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 12/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/17/2020 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 12/23/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 12/23/2020 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 1/13/2021 | Approved | JOE VELASQUEZ |
| Final | 2/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 3/22/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 3/22/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 3/22/2021 | Approved | KENNETH ROBERTS |