1320 E NEWTON ST 90021
Certificate Information: 1320 E NEWTON ST 90021
- Application / Permit
- 18016-10000-23726
- Plan Check / Job No.
- B18LA15298
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Change of use from Office/warehouse/garage to office building with assembly areas. Tenant improvement of the building which includes new interior walls, ceiling finishes and fixtures. Minor structural work.
- Permit Issued
- Issued on 1/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 6/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2018 | APPLICANT |
| Green Plans Picked Up | 8/2/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 8/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | QUAN NGHIEM |
| Corrections Issued | 9/5/2018 | QUAN NGHIEM |
| Quality Review Completed | 9/7/2018 | SHAHEN AKELYAN |
| Building Plans Picked Up | 9/11/2018 | APPLICANT |
| Applicant returned to address corrections | 10/16/2018 | QUAN NGHIEM |
| Plan Check Approved | 10/31/2018 | QUAN NGHIEM |
| Issued | 1/23/2019 | LADBS |
| TCO Issued (Expire Date: 12-22-2019) | 6/25/2019 | WINSTON DUNNING |
| CofO in Progress | 11/25/2019 | WINSTON DUNNING |
| CofO Issued-Status Void | 11/25/2019 | WINSTON DUNNING |
| Permit Finaled-Status Void | 11/25/2019 | WINSTON DUNNING |
| Re-Activate Permit | 6/29/2020 | DAVID TSAU |
| CofO Corrected | 6/29/2020 | DAVID TSAU |
| Permit Finaled | 6/29/2020 | DAVID TSAU |
Permit Application Clearance Information
| "D" conditions | Cleared | 9/11/2018 | EDBER MACEDO |
| Sewer availability | Cleared | 9/11/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2018 | MICHAEL CASTILLO |
| Project located in CRA area | Cleared | 9/12/2018 | JIM URQUHART |
| Green Code | Cleared | 10/4/2018 | KHEDER ALRAZAA |
| DAS Clearance | Cleared | 10/9/2018 | SOMKIAT SUPANYACHOTSKUL |
Contact Information
| Architect | , ; Lic. No.: C34612 | 1605 CLAY STREET #5 OAKLAND, CA 94612 |
| Contractor | Pankow Charles Builders Ltd; Lic. No.: 688972-B | 199 S LOS ROBLES AVE #300 PASADENA, CA 91101 |
| Engineer | Van, Bibber Mark Steven; Lic. No.: S5314 | 1120 MONTEREY DR EL CAJON, CA 92020 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/4/2019 | Partial Approval | DANIEL COLLINS |
| Green Building Rough | 3/8/2019 | Approved | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 3/13/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 3/14/2019 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 3/14/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 3/15/2019 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 3/15/2019 | Conditional Approval | KATY RAMIREZ |
| Drywall Nailing | 3/19/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 3/19/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Grading | 3/26/2019 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 3/27/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 3/29/2019 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/1/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 4/4/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Masonry | 4/9/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Masonry | 4/10/2019 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/10/2019 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 4/10/2019 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 4/15/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 4/25/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 4/25/2019 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 5/13/2019 | Not Ready for Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 5/16/2019 | Approved | DANIEL COLLINS |
| Drywall Nailing | 6/24/2019 | Approved | DANIEL COLLINS |
| Final | 6/24/2019 | Not Ready for Inspection | DANIEL COLLINS |
| Green Building Final | 6/24/2019 | No Access for Inspection | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2019 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 6/24/2019 | Approved | DANIEL COLLINS |
| Wood Frame | 6/24/2019 | Approved | DANIEL COLLINS |
| Final | 11/20/2019 | Conditional Approval | DANIEL COLLINS |
| Green Building Final | 11/20/2019 | Approved | DANIEL COLLINS |