14420 W VALERIO ST 91405
Certificate Information: 14420 W VALERIO ST 91405
- Application / Permit
- 18016-10000-23724
- Plan Check / Job No.
- B18LA15296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 6 (N) OMF AND 16 (N) SCCS TOTAL FOR ALL BUILDINGS.
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- Current Status
- CofC Issued on 11/16/2021
Permit Application Status History
| Submitted | 7/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | JAIME OROZCO |
| Corrections Issued | 9/5/2018 | JAIME OROZCO |
| Quality Review Completed | 9/6/2018 | SAI KHUM |
| Building Plans Picked Up | 9/10/2018 | APPLICANT |
| Plan Check Approved | 9/18/2018 | JAIME OROZCO |
| Issued | 8/27/2020 | APPLICANT |
| OK for CofC | 11/4/2021 | KENNETH ROBERTS |
| OK to Issue CofC | 11/6/2021 | KENNETH ROBERTS |
| CofC Issued | 11/16/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/4/2020 | MICHAEL GREGERSON |
| Abandoned oil well | Cleared | 7/27/2020 | KURT CORRAL |
| Abandoned oil well approval | Cleared | 7/27/2020 | KURT CORRAL |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Mnatsakanyan, Arthur; Lic. No.: C74802 | 409 W BROADWAY GLENDALE, CA 91204 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 12/3/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 12/29/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 12/29/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 12/29/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 4/22/2021 | Approved | JOE VELASQUEZ |
| Final | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| METHANE-Final | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 5/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 6/4/2021 | Partial Approval | HAMID PISHEHVAR |
| METHANE-Final | 6/4/2021 | Approved | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Approved | HAMID PISHEHVAR |
| Smoke Detectors | 6/4/2021 | Approved | HAMID PISHEHVAR |
| Final | 8/17/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 11/4/2021 | OK for CofC | KENNETH ROBERTS |