233 S UNION PL 90026

Certificate Information: 233 S UNION PL 90026

Application / Permit
18016-10000-23216
Plan Check / Job No.
B18LA14881
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT PER LAMC DIV 93. Install 5 (N) SCCS.
Permit Issued
Issued on 1/10/2020
Issuing Office
Metro
Current Status
CofC Issued on 7/28/2020

Permit Application Status History

Submitted 7/20/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 JAIME OROZCO
Corrections Issued 9/11/2018 JAIME OROZCO
Quality Review Completed 9/13/2018 SAI KHUM
Building Plans Picked Up 9/18/2018 APPLICANT
Applicant returned to address corrections 10/3/2018 JAIME OROZCO
Plan Check Approved 1/4/2019 JAIME OROZCO
Issued 1/10/2020 LADBS
OK for CofC 5/27/2020 DARRYL ARNOLD
OK to Issue CofC 6/12/2020 ERNESTO CORRAL
CofC Issued 7/28/2020 ERNESTO CORRAL

Permit Application Clearance Information

Project located in CRA area Cleared 10/5/2018 JIM URQUHART
Housing rent stabilization Cleared 1/10/2020 STEVEN HOFSTAD

Contact Information

Contractor Ces4 Construction; Lic. No.: 1042127-B 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356
Engineer Ni, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2020 Approved BRUCE CAMPBELL
Deputy Steel/Welding 3/4/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 3/25/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 3/25/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 3/27/2020 Conditional Approval MARK FERRARI
Deputy Wood Construction 3/31/2020 Conditional Approval MARK FERRARI
Wood Frame 4/2/2020 Approved DARRYL ARNOLD
Interior/Exterior Lathing 5/14/2020 Approved DARRYL ARNOLD
Final 5/27/2020 OK for CofC DARRYL ARNOLD
METHANE-Final 5/27/2020 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/27/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 5/27/2020 Approved DARRYL ARNOLD
Final 6/5/2020 Not Ready for Inspection DARRYL ARNOLD