6552 W LA MIRADA AVE 90038

Certificate Information: 6552 W LA MIRADA AVE 90038

Application / Permit
18016-10000-22686
Plan Check / Job No.
B18LA14476
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. 4 CANTILEVER COLUMNS
Permit Issued
Issued on 7/20/2020
Issuing Office
Metro
Current Status
CofC Issued on 2/10/2021

Permit Application Status History

Submitted 7/18/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 JOHN FRANCIA
Corrections Issued 9/4/2018 JOHN FRANCIA
Quality Review Completed 9/7/2018 SAI KHUM
Building Plans Picked Up 9/11/2018 APPLICANT
Plan Check Approved 9/18/2018 JOHN FRANCIA
Issued 7/20/2020 APPLICANT
OK for CofC 2/9/2021 JONATHAN QUACH
CofC Issued 2/10/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 6/8/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Pacific Coast Developers; Lic. No.: 888234-B 5249 BECKFORD AVENUE      TARZANA, CA 91356
Engineer Farmand, Anthony E; Lic. No.: C62595 4675 MACARTHUR COURT SUITE 800      NEWPORT BEACH, CA 92660

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/30/2020 Approved EDWIN GREGORYONA
Deputy Steel/Welding 10/9/2020 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 10/16/2020 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 10/16/2020 Corrections Issued JONATHAN QUACH
Structural Steel Frame 10/16/2020 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 10/21/2020 Approved JONATHAN QUACH
Footing/Foundation/Slab 10/21/2020 Approved JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Approved JONATHAN QUACH
Wood Frame 12/18/2020 Approved JONATHAN QUACH
Deputy Wood Construction 12/21/2020 Conditional Approval JONATHAN QUACH
Interior/Exterior Lathing 12/23/2020 Corrections Issued JONATHAN QUACH
Final 1/7/2021 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 1/7/2021 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 1/7/2021 Not Ready for Inspection JONATHAN QUACH
Final 2/9/2021 OK for CofC JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 2/9/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 2/9/2021 Approved JONATHAN QUACH