6552 W LA MIRADA AVE 90038
Certificate Information: 6552 W LA MIRADA AVE 90038
- Application / Permit
- 18016-10000-22686
- Plan Check / Job No.
- B18LA14476
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. 4 CANTILEVER COLUMNS
- Permit Issued
- Issued on 7/20/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/10/2021
Permit Application Status History
| Submitted | 7/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | JOHN FRANCIA |
| Corrections Issued | 9/4/2018 | JOHN FRANCIA |
| Quality Review Completed | 9/7/2018 | SAI KHUM |
| Building Plans Picked Up | 9/11/2018 | APPLICANT |
| Plan Check Approved | 9/18/2018 | JOHN FRANCIA |
| Issued | 7/20/2020 | APPLICANT |
| OK for CofC | 2/9/2021 | JONATHAN QUACH |
| CofC Issued | 2/10/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/8/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Pacific Coast Developers; Lic. No.: 888234-B | 5249 BECKFORD AVENUE TARZANA, CA 91356 |
| Engineer | Farmand, Anthony E; Lic. No.: C62595 | 4675 MACARTHUR COURT SUITE 800 NEWPORT BEACH, CA 92660 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/30/2020 | Approved | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 10/16/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/16/2020 | Corrections Issued | JONATHAN QUACH |
| Structural Steel Frame | 10/16/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 10/21/2020 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/21/2020 | Approved | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 12/18/2020 | Approved | JONATHAN QUACH |
| Deputy Wood Construction | 12/21/2020 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 12/23/2020 | Corrections Issued | JONATHAN QUACH |
| Final | 1/7/2021 | Not Ready for Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/7/2021 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 1/7/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 2/9/2021 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 2/9/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 2/9/2021 | Approved | JONATHAN QUACH |