515 S KINGSLEY DR 90020

Certificate Information: 515 S KINGSLEY DR 90020

Application / Permit
18016-10000-22423
Plan Check / Job No.
B18LA14321
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft Story retrofit as per LABC CH 93. Moment frame and Shear wall.
Permit Issued
Issued on 7/14/2022
Issuing Office
Metro
Current Status
CofC Issued on 6/23/2023

Permit Application Status History

Submitted 7/13/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 SAMUEL GONZALEZ
Corrections Issued 9/4/2018 SAMUEL GONZALEZ
Quality Review Completed 9/7/2018 SAI KHUM
Building Plans Picked Up 9/12/2018 APPLICANT
Plan Check Approved 2/14/2019 SAMUEL GONZALEZ
Issued 7/14/2022 APPLICANT
OK for CofC 6/22/2023 DARRYL ARNOLD
CofC Issued 6/23/2023 WINSTON DUNNING

Permit Application Clearance Information

Project located in CRA area Cleared 10/10/2018 JIM URQUHART
Housing rent stabilization Cleared 2/6/2020 MICHAEL GREGERSON

Contact Information

Contractor Twenty One Retrofit Inc; Lic. No.: 1065687-B 17700 S AVALON BLVD UNIT #345      CARSON, CA 90746
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/2/2022 Corrections Issued BRUCE CAMPBELL
Deputy Drilled-In Anchors 8/12/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 8/16/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 10/14/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 10/20/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 10/24/2022 Approved DARRYL ARNOLD
Deputy Steel/Welding 10/28/2022 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Approved DARRYL ARNOLD
Structural Steel Frame 11/8/2022 Approved DARRYL ARNOLD
Wood Frame 11/8/2022 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Corrections Issued VAHE KELEDJIAN
Deputy Wood Construction 12/5/2022 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/21/2022 Conditional Approval VAHE KELEDJIAN
Interior/Exterior Lathing 12/28/2022 Conditional Approval DARRYL ARNOLD
Final 2/8/2023 Corrections Issued VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved VAHE KELEDJIAN
Smoke Detectors 2/8/2023 Approved VAHE KELEDJIAN
Final 2/15/2023 Partial Approval JAIME RIOS
Final 4/5/2023 Corrections Issued VAHE KELEDJIAN
Final 6/12/2023 Not Ready for Inspection DARRYL ARNOLD
Final 6/22/2023 OK for CofC DARRYL ARNOLD