515 S KINGSLEY DR 90020
Certificate Information: 515 S KINGSLEY DR 90020
- Application / Permit
- 18016-10000-22423
- Plan Check / Job No.
- B18LA14321
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft Story retrofit as per LABC CH 93. Moment frame and Shear wall.
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/23/2023
Permit Application Status History
| Submitted | 7/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | SAMUEL GONZALEZ |
| Corrections Issued | 9/4/2018 | SAMUEL GONZALEZ |
| Quality Review Completed | 9/7/2018 | SAI KHUM |
| Building Plans Picked Up | 9/12/2018 | APPLICANT |
| Plan Check Approved | 2/14/2019 | SAMUEL GONZALEZ |
| Issued | 7/14/2022 | APPLICANT |
| OK for CofC | 6/22/2023 | DARRYL ARNOLD |
| CofC Issued | 6/23/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 10/10/2018 | JIM URQUHART |
| Housing rent stabilization | Cleared | 2/6/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Twenty One Retrofit Inc; Lic. No.: 1065687-B | 17700 S AVALON BLVD UNIT #345 CARSON, CA 90746 |
| Engineer | Park, Juntae; Lic. No.: C65104 | 1444 HI POINT ST LOS ANGELES, CA 90035 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/2/2022 | Corrections Issued | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 8/12/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/16/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 10/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/20/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/24/2022 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 10/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 11/8/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/8/2022 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Wood Construction | 12/5/2022 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/21/2022 | Conditional Approval | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 12/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/8/2023 | Corrections Issued | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 2/8/2023 | Approved | VAHE KELEDJIAN |
| Final | 2/15/2023 | Partial Approval | JAIME RIOS |
| Final | 4/5/2023 | Corrections Issued | VAHE KELEDJIAN |
| Final | 6/12/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 6/22/2023 | OK for CofC | DARRYL ARNOLD |