5744 N LAUREL CANYON BLVD 91607
Certificate Information: 5744 N LAUREL CANYON BLVD 91607
- Application / Permit
- 18016-10000-21816
- Plan Check / Job No.
- B18LA13899
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIVISION 93. RETROFIT CONSISTS OF INSTALLING (2) ONE BAY ORDINARY MOMENT FRAME AND (12) SPECIAL STEEL CANTILEVER COLUMNS TO AN EXISTING 3-STORY APARTMENT BUILDING
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/9/2021
Permit Application Status History
| Submitted | 7/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | ERIC WONG |
| Corrections Issued | 8/27/2018 | ERIC WONG |
| Quality Review Completed | 8/31/2018 | SAI KHUM |
| Building Plans Picked Up | 9/17/2018 | APPLICANT |
| Plan Check Approved | 7/5/2019 | ERIC WONG |
| Issued | 1/16/2020 | LADBS |
| OK for CofC | 10/20/2021 | KENNETH ROBERTS |
| CofC Issued | 12/9/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 5/23/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 12/26/2019 | STEVEN HOFSTAD |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/19/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 8/19/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/19/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/11/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/14/2020 | Approved | JOE VELASQUEZ |
| Deputy Steel/Welding | 9/21/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Approved | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/22/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 10/8/2020 | Approved | JOE VELASQUEZ |
| Wood Frame | 12/22/2020 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 2/5/2021 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Approved | HAMID PISHEHVAR |
| Footing/Foundation/Slab | 2/17/2021 | Approved | HAMID PISHEHVAR |
| Structural Steel Frame | 2/17/2021 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Concrete | 2/19/2021 | Approved | HAMID PISHEHVAR |
| Wood Frame | 3/5/2021 | Partial Approval | JOE VELASQUEZ |
| Insulation | 3/8/2021 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 3/8/2021 | Partial Approval | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 4/6/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 4/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 4/6/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 4/7/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 4/14/2021 | Partial Approval | JOE VELASQUEZ |
| Structural Steel Frame | 4/14/2021 | Partial Approval | JOE VELASQUEZ |
| Interior/Exterior Lathing | 5/14/2021 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 5/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 5/20/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/15/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Steel/Welding | 6/28/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 6/29/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/14/2021 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/15/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 7/15/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/20/2021 | No Access for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 9/3/2021 | Approved | JOE VELASQUEZ |
| Final | 9/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/14/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 9/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 10/20/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/20/2021 | Approved | KENNETH ROBERTS |